ποΈ PROJECT SPOTLIGHT: 147 Golf Road, New Lynn ποΈ
We're incredibly proud to showcase our latest achievement β 5 stunning standalone houses at 147 Golf Road, New Lynn!
β‘ PROACTIVE SAFETY LEADERSHIP β‘
This project presented a unique challenge: overhead powerlines just 3.8m from the building. Rather than seeing this as an obstacle, we turned it into an opportunity to demonstrate excellence in safety management.
Our Proactive Approach:
β
4 months advance planning β engaged with Vector and WSP well ahead of construction
β
Comprehensive documentation including:
β’ Alternative scaffolding drawings & schematics
β’ Detailed Health & Safety Plan
β’ Work Method Statements for all trades
β’ Delivery space planning & scaffolding dos/don'ts
β’ Emergency procedures & nearest hospital information
β
Close Approach Consent β successfully obtained approval through thorough preparation
β
Ongoing compliance β 28-day onsite meetings with Vector throughout the project
π
PROJECT TIMELINE:
β’ Foundation β Framing β Roofing β Cladding β Services β Fitoff
β’ Final inspection passed βοΈ
β’ Code Compliance Certificate approved βοΈ
β’ From foundation to CCC: 6 months β±οΈ
The end result? Five beautiful homes delivered safely, efficiently, and with full regulatory compliance.
This project exemplifies our commitment to:
πΈ Proactive safety management
πΈ Collaborative stakeholder engagement
πΈ Meticulous planning and documentation
πΈ Quality construction delivery
A huge thank you to our team and all subcontractors who made this project a success! π
ResidentialConstruction SGPWorks PowerlineSafety ProjectManagement QualityHomes