01/11/2022
Massive few weeks for the team to get the slab down on our Te Roera drive Minor Dwelling. We made an ambitious goal and booked the diggers, concrete trucks, concrete placers, concrete pump, sparkies, plumbers and multiple engineer and council inspections about 4 weeks ago and just made it happen. There was a bit going on in this foundation as once the block work was up and filled with concrete we had to let the concrete cure sufficiently before back filling with the crushed aggregate- once we were able to start filling it was subject to Geo Technical Engineer testing every 500 mm in this case and then once we got hgh enough to reduce weight on the walls we actually continued back filling with large slabs of polystyrene- Dpm then goes down and more polystyrene, more steel and then boom ready for the slab once services are all positioned correctly.. steel portals are on site and ready to go up and frames turn up Thursday so things are heating up up here🔥👊🔨