18/08/2026
Rangitanuku Project update..stage 1 is nearing it's completion..back door installed..Gib all done..tiler has started in the bathroom..plasterer starts tomorrow. Massive pivot front door arrived..underfloor insulation still in progress but it's not an urgent job so is being done during down time. Stage 2 was started in the weekend when the client went mad with enthusiasm...kitchen removed and some demo done lol..the spaces are really starting to emerge and give an idea of the homes new makeup..it's been a frosty couple of weeks π₯Άπ₯Ά