Project Progress Update β Culvert Installation π§
Good progress has been made on site despite the challenging waterlogged conditions.
Our team successfully diverted the water flow and constructed a temporary access road to allow equipment and materials to reach the work area. Continuous dewatering through pumping was carried out to maintain safe and workable site conditions.
To strengthen and protect the structure, gabion baskets were installed at both the inlet and outlet to control erosion and stabilize the saturated ground.
We have now successfully installed two (2) 900mm culverts, and backfilling works are currently underway.
The headwalls and wing walls will be constructed during the next stage, together with the installation of the concrete apron to complete the structure.