14/08/2026
General Trias Site | 3-Storey Residential Project
WEEK 31 UPDATE (Post 1/2)
3/F Electrical Works & Concrete Works on Plaswalls
Electrical works and concrete works on the Plaswalls continued on the third floor this week. We’re a little behind on the updates, but the project is well ahead of schedule. Structural completion is just around the corner!