31/05/2026
Weekly update: House Construction
1st unit:
🧱Masonry works: Windows and Wall Cornering
🧱Interior Wall Plastering
🧱Septic Tank excavation and flooring concreting
🧱Back Door: Jamb installation
🧱Kitchen counter construction
2nd unit:
🧱2F Beam Formworks Installation
🧱Shoring Jack Installation
🧱Steeldeck installation
🧱2F Plumbing and electrical roungins installation