Surneco Sub Area Office Parang. Electric Distribution Utility and Electric Service Provider

UNSCHEDULED POWER INTERRUPTIONReporting: SAO1Date/Time reported : Oct. 12, 2025 09:15 pmPeriod time (from) : 07:11 PMPer...
12/10/2025

UNSCHEDULED POWER INTERRUPTION

Reporting: SAO1
Date/Time reported : Oct. 12, 2025 09:15 pm
Period time (from) : 07:11 PM
Period time (to) : 8:24 PM
Affected area/s: Panatao to Cagdianao, Claver, SdN
Cause : Broken pin type insulator and pole top pin @ P3, Cabugo, Claver, SdN
Action taken: Replace pin type insulator and pole top pin

FYI..

UNSCHEDULED POWER INTERRUPTIONReporting: SAO1Date/Time reported : Oct. 5, 2025 09:41 amFirst trip off/interruption:Perio...
05/10/2025

UNSCHEDULED POWER INTERRUPTION

Reporting: SAO1
Date/Time reported : Oct. 5, 2025 09:41 am

First trip off/interruption:
Period time (from) : 7:27AM
Period time (to) : 7:28 AM

Second trip off/interruption: Single phasing, recloser manually open due to burned cut-out @ Daywan, Claver, SdN sectionalizer
Period time (from): 8:20AM
Period time (to): 9:25AM

Affected area/s: Tayaga, Bagacay, Ladgaron, Magallanes, Daywan, Sapa, Claver, SdN and all baragays of Gigaquit, SdN

Cause : Burned cut-out @ Daywan, Claver, SdN due to electricuted crow bird at Dalit, San-Isidro, Gigaquit, SdN
Action taken: Replace burned cut-out

FYI..

UNSCHEDULED POWER INTERRUPTIONReporting: SAO1Date/Time reported : Sept. 15, 2025 08:31 amPeriod time (from) : 11:09 PMPe...
15/09/2025

UNSCHEDULED POWER INTERRUPTION

Reporting: SAO1
Date/Time reported : Sept. 15, 2025 08:31 am
Period time (from) : 11:09 PM
Period time (to) : 3:30 am
Affected area/s: Tayaga, Bagacay, Ladgaron, Magallanes, Daywan, Claver, SdN and all baragays of Gigaquit, SdN
Cause : Broken/damage four(4) unit of cut-out hit by lightning at brgy. Tayaga, Claver, SdN
Action taken: Replace broken and damage cut-out

FYI..

14/09/2025

Unscheduled power interruption affecting parts of Surigao del Norte and portions of Surigao del Sur, 14 September 2025, Sunday.

Time of outage: 5:27PM

Affected:

SURNECO (Claver Substation)

SIARELCO (entire franchise area)

SURSECO 2 (Carrascal and Madrid Substations)

Reason: Outage of Placer-Madrid 69kV Line.

Line patrol ongoing.


14/09/2025

UNSCHEDULED POWER INTERRUPTION

Reporting: SAO1
Date/Time reported : Sept. 14, 2025 07:12 pm
Period time (from) : 5:26 PM
Period time (to) :
Affected area/s: All barangays of Claver and Gigaquit, SdN
Cause : NGCP unscheduled power interruption
Action taken:

FYI..

UNSCHEDULED POWER INTERRUPTIONReporting: SAO1Date/Time reported : Sept. 13, 2025 10:12 amPeriod time (from) : 1:40 AMPer...
13/09/2025

UNSCHEDULED POWER INTERRUPTION

Reporting: SAO1
Date/Time reported : Sept. 13, 2025 10:12 am
Period time (from) : 1:40 AM
Period time (to) : 3:00 AM
Affected area/s: Brgy. Panatao to Cagdianao, Claver, SdN
Cause : Line to line fault due to broken oval eye bolt of C4-structure located at Dinangdangan, Cabugo, SdN.
Action taken: Replace broken oval eye bolt

FYI..

UNSCHEDULED POWER INTERRUPTIONReporting: SAO1Date/Time reported : Sept. 8, 2025 9:12 amPeriod time (from) : 1:10 AMPerio...
08/09/2025

UNSCHEDULED POWER INTERRUPTION

Reporting: SAO1
Date/Time reported : Sept. 8, 2025 9:12 am
Period time (from) : 1:10 AM
Period time (to) : 2:51 AM
Affected areas : Brgy. Urbiztondo, Taganito, Hayanggabon, Cagdianao
Cause : Broken/burned pin type insulator at P6, Taganito, Claver, SdN
Action taken: Replace pin type insulator and pole tap pin

FYI..

POWER INTERRUPTIONPerson Reporting : DedumoDate/Time reported : Aug.25, 2025 7:40 amPeriod time (from) : 6:12AMPeriod ti...
24/08/2025

POWER INTERRUPTION

Person Reporting : Dedumo
Date/Time reported : Aug.25, 2025 7:40 am
Period time (from) : 6:12AM
Period time (to) : 6:23 amM
Affected areas : Tayaga, Bagacay, Ladgaron, Magallanes, Daywan, and other Barangays of Gigaquit, SdN
Cause : Cut Off primary line @ Poniente, Gigaquit, SdN

Further Information: Emergency Power Interruption

Time: 8:00 am
Estimated time to restore: 9:30am
Cause: To fix the said cut off primary @ Poniente, Gigaquit, SdN
Affected Areas: Brgy. Daywan and all barangays of Gigaquit, SdN.

FYI..

23/08/2025

power interruption schedule
SURNECO bad--as Restoration Update:
What: emergency Power Interruption
Outage Date and Time: August 23, 2025; 7:45 AM
Source: Ipil sectionalizer
Cause: Emergency replacement of leaning C1 primary line along Amoslog area
Restoration Time completed: 11:45am
Affected Areas and Restoration Status: mun of bacuag and Amoslog to pananay-an

We apologize for any inconvenience caused during this interruption and appreciate your patience and understanding.
Thank you for your cooperation!

Address

Surigao City
8409

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Telephone

+639631065520

Alerts

Be the first to know and let us send you an email when Surneco Sub Area Office Parang. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share

Category