Surseco 2, Inc.

Surseco 2, Inc. Surigao del Sur II Cooperative, Inc. It was registered with the National Electrification Administration (NEA) as the 115th electric cooperative in the country.

HOTLINE NUMBERS:
Cortes, Tandag, Tago: 09487682646 and 09853565772
CCMCL: 09331980090
Lianga: 09326580064
San Agustin: 09326580091
San Miguel: 09326577377
Bayabas, Cagwait, Marihatag: 09326580028 or 09455794755 (Globe HOTLINE NUMBERS:

Cortes, Tandag, Tago: 09487682646 and 09853565772
CCMCL: 09331980090
Lianga: 09326580064
San Agustin: 09326580091
San Miguel: 09326577377
Bayabas, Cagwa

it, Marihatag: 09326580028 or 09455794755 (Globe)

***********************
๐™Ž๐™๐™๐™Ž๐™€๐˜พ๐™Š ๐™„๐™„ ๐™‚๐™š๐™ฃ๐™š๐™ง๐™–๐™ก ๐™„๐™ฃ๐™›๐™ค๐™ง๐™ข๐™–๐™ฉ๐™ž๐™ค๐™ฃ

๐™„๐™ฃ๐™˜๐™ค๐™ง๐™ฅ๐™ค๐™ง๐™–๐™ฉ๐™ž๐™ค๐™ฃ

Pursuant to the provisions of Republic Act 6038 as amended by Presidential Decree 269; and similar to the experience of other electric cooperatives, SURSECO II was organized on September 10, 1979 as a private, non-stock, non-profit membership and service-oriented cooperative, and an implementing arm of the governmentโ€™s Rural Electrification Program (REP) to realize the national policy objective for the total electrification of the Philippines on an area coverage basis. It is presently classified and categorized by the NEA as a Large; AAA electric cooperative; and belongs to the Best Region of Caraga.


๐™’๐™๐™ฎ โ€œ๐™€๐™ก๐™š๐™˜๐™ฉ๐™ง๐™ž๐™˜ ๐˜พ๐™ค๐™ค๐™ฅ๐™š๐™ง๐™–๐™ฉ๐™ž๐™ซ๐™š (๐™€๐˜พ)โ€? The rural electrification program has considered the โ€œcoopโ€ as the logical form of organization to achieve area coverage electrification because being owned by the member-consumer-owners (MCOs), ECs are committed to pursue total electrification as opposed to a profit-motivated private utility enterprise and could generate MCO and public support and cooperation in project implementation.


๐™๐™ง๐™–๐™ฃ๐™˜๐™๐™ž๐™จ๐™š ๐˜ผ๐™ง๐™š๐™– ๐™–๐™ฃ๐™™ ๐™‹๐™ค๐™ฌ๐™š๐™ง ๐™Ž๐™ค๐™ช๐™ง๐™˜๐™š

As part of its initial energization program, SURSECO II took over the franchise of the power systems of the local governments of Tago, Marihatag and Carrascal; and a privately owned electric system in Tandag (now Tandag City, the capital of the province). Afterwards, it negotiated for the shipping of one (1) unit 3.75MVA (megavolt-ampere) power transformer from Aklan Electric Cooperative, Inc. (AKELCO) which was installed at the town of Madrid. Barely a year after its installation, on November 10, 1983, Carrascal, Cantilan, Madrid, Carmen and Lanuza (collectively called CARCANMADCARLAN) were energized and power was supplied by the National Power Corporation (NPC). With Republic Act 9136 or the Electric Power Industry Reform Act of 2001 (EPIRA), NPCโ€™s remaining power generation assets are now being managed by the Power Sector Assets and Liabilities Management Corp. (PSALM Corp.); and consequently, power generation transactions and contracts of SURSECO II, and other concerned ECs, transferred under the PSALM Corp. The franchise area of SURSECO II is situated along the coastal part of Surigao del Sur with a total land area of 2, 758.96 square kilometers. It is now serving roughly 74,000 consumers. Originally, SURSECO II has served 13 municipalities namely, San Agustin, Marihatag, Cagwait, Bayabas, San Miguel, Tago, Tandag, Cortes, Lanuza, Carmen, Madrid, Cantilan and Carrascal. But in 1989, the member-consumers of the municipality of San Agustin demanded to transfer to the coverage of SURSECO I. Then again, effective October 26, 2007, the municipality of San Agustin voluntarily returned to SURSECO II, tugging along the municipality of Lianga. Thus, at present, SURSECO II is serving 13 municipalities and Tandag City. Each municipality and Tandag City is being represented by one district representative. The electric power for the whole coverage area was distributed through the four substation power transformers respectively located at the municipalities of Madrid, Cagwait, Lianga and Tandag. The coop has 100% energization, excluding Barangay Lobo in the municipality of Cantilan, and Barangay Bitaugan in the municipality of San Miguel which were originally waived to the Department of Energy (DOE). Fortunately, the National Government is now aiming to energize these two barangays through the Sitio Electrification Program (SEP) through the NEA.

๐Ÿ”ดOFFICIAL STATEMENT: SURSECO IIโ€™S POWER STATUS AMIDST THE EL NIร‘O AND CAPACITY CHALLENGE_________________________WHAT SU...
15/05/2026

๐Ÿ”ดOFFICIAL STATEMENT: SURSECO IIโ€™S POWER STATUS AMIDST THE EL NIร‘O AND CAPACITY CHALLENGE
_________________________

WHAT SURSECO II IS DOING?

We are excited to inform you of the LONG-TERM AND SHORT-TERM solutions to address challenges in the power distribution system in terms of capacity, reliability, safety, service efficiency, system loss reductionโ€”and the present challenges brought about by the El Niรฑo.

LONG-TERM SOLUTIONS: These are strategic, high-impact projects designed to meet growing demand and provide a future-ready system.

1. PROJECT: (Capacity augmentation) Installation of a 5MVA Substation at Tago to accommodate present and future power requirement - Phase 1 of civil work is on-going

2. PROJECT: (Capacity augmentation) Tandag Substation Capacity Augmentation from 10MVA to 15MVA to accommodate present and future power requirement - Phase 1 of civil work is completed; Substation Construction and Primary Equipment Installation is ongoing

3. PROJECT: (Capacity augmentation) Rental of mobile power transformer to temporarily increase the capacity of Tandag 10MVA Substation pending the completion of the new 15MVA Substation (related to item 2) - For energization pending the metering installation requirements of the National Grid Corporation of the Philippines (NGCP)

4. PROJECT: (Reliability) Buffer Stock Requirement (per NEA Memo No. 2015-023) in case of calamities - Available

5. PROJECT: (Safety) Installation of 69 kV Circuit Breaker at Cagwait Substation (Compliance of Philippine Grid Code 2016 Edition) - Completed

6. PROJECT: (Safety) Installation of Circuit Breakers on Backbone Line Safety - Completed

7. PROJECT: (Safety) Replacement of Deteriorated Distribution Poles - Continuous activity

8. PROJECT: (Safety) Replacement of line conductors (from bare to insulated) that have critical clearances from structures and tall-growing vegetations therefore susceptible to line fault and pose public hazard - Continuous activity

9. PROJECT: (Safety) Re-routing and Rehabilitation of Electrical Facilities that are situated in private properties and are now aging as they were installed during the early years of SURSECO IIโ€™s operation - Continuous activity

10. PROJECT: (System Loss) Kilowatt-hour Meter Replacement - Continuous activity

11. PROJECT: (Safety and Reliability and System Loss Reduction) Regular clearing of Power Line Corridors (PLC) that have critical clearances from tall-growing vegetations, therefore susceptible to line fault and pose public hazard - Continuous activity

SHORT-TERM SOLUTIONS:

SURSECO II also conducted and implemented the following short-term solutions to manage transformer loading in parallel to the ongoing long-term solutions to manage peak electricity demand:

[Note: Peak electricity demand refers to the highest level of electricity usage at a specific time across an electrical grid or system. It is the time when the demand for power is at its maximumโ€”usually when many homes, businesses, and industries are using electricity simultaneouslyโ€”and is especially increased during SUMMER.]

1. Enhancement of substation cooling system via forced-air fan installation to mitigate thermal stress and improve capacity.

2. Adjustment of feeder configurations to minimize peak current per phase.

3. Identified big loads and industrial type consumers were requested to schedule their heavy operations during off-peak hours.

4. Voltage correction activities to accommodate the operation of said big loads and industrial-type consumers during daytime.

5. Manual load droppingโ€”if necessary and urgentโ€”of select locations at a certain but short duration (this will be broadcasted via TEXT BLAST to concerned MCOs).

6. Continuous load monitoring of all substations.
_________________________

SERIES OF POWER INTERRUPTIONS: WHAT IS HAPPENING?

1. Impact of El Niรฑo on SURSECO II System Reliability

The extreme heat brought by El Niรฑo has significantly increased electricity demand across the SURSECO II franchise area. In fact, the Tandag City Disaster Risk Reduction and Management Office has published a heat index of 44 ยฐC (Orange or Danger Level). As MCOs continuously use air conditioners, fans, and other cooling equipment to combat the rising temperatures, the load on our network has reached critical levels.

Why Outages Occur During Extreme Heat?

1) Substation and Facility Overloading: The sudden, widespread surge in power consumption can exceed the designed capacity of our substations and distribution lines.

2) Protective Tripping: To prevent expensive equipment from exploding or burning out due to this overload, our systemโ€™s protective devices (like circuit breakers) are designed to โ€œtripโ€ or automatically shut off. While this causes a temporary power outage, it is a necessary safety measure to avoid long-term damage to the grid.

3) Reduced Equipment Efficiency: Electrical hardware naturally struggles in high ambient temperatures. Prolonged heat makes transformers and conductors less efficient and more prone to technical stress, further increasing the risk of service interruptions.

The Heat is On: Understanding System Stress in the SURSECO II Service Area

The intense heat brought by El Niรฑo is doing more than just making us uncomfortableโ€”it is pushing our power grid to its absolute limits. As temperatures soar, the demand for cooling has created a โ€œperfect stormโ€ for our infrastructure, particularly in towns with high power demand.

2. Peak Hour Outages and the Double Challenge of Local Load vs. Power Transmission Issues

As disclosed in our transparency statements, the Cagwait 5MVA and Tandag 10MVA Substations are already at full capacity, hence the ongoing development of additional substations. While our substations are built to handle local needs,

โ€ข The El Niรฑo has accelerated electricity use beyond forecasted levels. When demand exceeds what the substations can safely provide, protective devices โ€œtripโ€ to prevent a catastrophic system failure or fire.

โ€ข With Surigao del Sur as a rapidly growing economic hub, a surge in infrastructure and business means higher energy needs.

โ€ข On top of local overloading, SURSECO IIโ€™s franchise areaโ€”being at the โ€œtail endโ€ of NGCPโ€™s power transmission lineโ€”is the most vulnerable to voltage drops and technical stress.
_________________________

OUR COMMITMENT AND APPEAL TO THE MCOS

SURSECO II continues to closely monitor our facilities to manage the thermal stresses affecting the system. We also encourage our MCOs to practice energy efficiency during peak hours to help ease the load on our distribution network and support a more stable power supply.

The ongoing El Niรฑo has placed additional pressure on our operations, but it also underscores the importance of strengthening our system. While SURSECO II has already outlined both short-term and long-term technical measures, achieving reliable service is a shared responsibility. By understanding the conditions we are working through, we can move forward togetherโ€”addressing the challenges of this heatwave and building a more resilient power system.

ROEL E. ABAD
General Manager

OFFICIAL POST OF THE National Grid Corporation of the Philippines REGARDING THE PRESENT UNSCHEDULED POWER INTERRUPTION A...
14/05/2026

OFFICIAL POST OF THE National Grid Corporation of the Philippines REGARDING THE PRESENT UNSCHEDULED POWER INTERRUPTION AFFECTING SURSECO2'S NORTH AREA (Carrascal, Cantilan, Madrid, Carmen, and Lanuza)

********

โ€ผ๏ธโ‰๏ธ FOR VERIFICATION OR COMPLAINS regarding this UNSCHEDULED POWER INTERRUPTION, kindly directly coordinate with NGCP through their official FB Page or Website. โ€ผ๏ธโ‰๏ธ

*******
FOR POWER INTERRUPTIONS NOT RELATED TO THIS POST, PLEASE CHECK:
Surseco2 Kuryente Patrol - Cortes, San Miguel, Tago, Tandag City
Surseco2 Kuryente Patrol - Bayabas, Cagwait, San Agustin, Lianga

Unscheduled power interruption affecting parts of Surigao del Norte and portions of Surigao del Sur, 14 May 2026, Thursday, at 9:56 PM.

Affected EC:
โ€ข SURNECO Claver Substation
โ€ข SIARELCO
โ€ข SURSECO 2 Carrascal and Madrid Substations

Reason: Outage of Placer-Madrid 69kV Line

Line patrol ongoing.

๐—ฃ๐—ข๐—ช๐—˜๐—ฅ ๐—”๐—Ÿ๐—˜๐—ฅ๐—ง FROM THE National Grid Corporation of the Philippines********  โ€ผ๏ธโ‰๏ธFOR VERIFICATION OR COMPLAINS regarding t...
14/05/2026

๐—ฃ๐—ข๐—ช๐—˜๐—ฅ ๐—”๐—Ÿ๐—˜๐—ฅ๐—ง FROM THE National Grid Corporation of the Philippines
********

โ€ผ๏ธโ‰๏ธFOR VERIFICATION OR COMPLAINS regarding this POWER INTERRUPTION, kindly directly coordinate with NGCP through their official FB Page or Website. โ€ผ๏ธโ‰๏ธ
********

DATE: MAY 17, 2026 (SUNDAY)

TIME: 8:00 AM to 6:00 PM

Be informed that this NGCP Power Interruption will AFFECT SURSECO II MCOs of the following areas:
โ€ข LIANGA
โ€ข SAN AGUSTIN
โ€ข MARIHATAG
โ€ข CAGWAIT
โ€ข BAYABAS
โ€ข SAN MIGUEL
โ€ข TAGO
โ€ข CORTES
โ€ข TANDAG CITY

๏ผด๏ผจ๏ผก๏ผฎ๏ผซ ๏ผน๏ผฏ๏ผต!

*******
FOR POWER INTERRUPTIONS NOT RELATED TO THIS POST, PLEASE CHECK:
Surseco2 Kuryente Patrol - CCMCL
Surseco2 Kuryente Patrol - Bayabas, Cagwait, San Agustin, Lianga
Surseco2 Kuryente Patrol - Cortes, San Miguel, Tago, Tandag City

Rescheduled Power Interruption in Tandag City and parts of Surigao del Sur

The scheduled maintenance activity on the NGCP San Franciscoโ€“Tandag 69kV Line, affecting SURSECO 2 ( Surseco 2, Inc. ) (Lianga, Cagwait, and Tandag Substations) on 16 May 2026, Saturday, has been rescheduled upon the request of COMELEC Surigao del Sur.

The new schedule will be on 17 May 2026, Sunday, 8:00 AM to 6:00 PM.

14/05/2026

TAKNA SA SURSECO II

๐ƒ๐ˆ๐’๐‚๐‹๐€๐ˆ๐Œ๐„๐‘:
ยฉ ๐ˆ ๐๐ข๐๐ง'๐ญ ๐จ๐ฐ๐ง ๐ญ๐ก๐ž ๐‚๐Ž๐๐˜๐‘๐ˆ๐†๐‡๐“ ๐Ÿ๐จ๐ซ ๐ญ๐ก๐ž๐ฌ๐ž ๐ฌ๐จ๐ง๐ ๐ฌ. ๐“๐ก๐ข๐ฌ ๐•๐ข๐๐ž๐จ ๐ข๐ฌ ๐ฉ๐ฎ๐ซ๐ž๐ฅ๐ฒ ๐Ÿ๐จ๐ซ information, education and communication ๐ฉ๐ฎ๐ซ๐ฉ๐จ๐ฌ๐ž๐ฌ ๐จ๐ง๐ฅ๐ฒ. ๐’๐ž๐œ. ๐Ÿ๐ŸŽ๐Ÿ• ๐จ๐Ÿ ๐‚๐จ๐ฉ๐ฒ๐ซ๐ข๐ ๐ก๐ญ ๐€๐œ๐ญ. ๐Ÿ๐Ÿ—๐Ÿ•๐Ÿ— ๐š๐ฅ๐ฅ๐จ๐ฐ ๐ญ๐ก๐ž๐ฌ๐ž ๐ฆ๐š๐ญ๐ž๐ซ๐ข๐š๐ฅ๐ฌ ๐Ÿ๐จ๐ซ ๐Ÿ๐š๐ข๐ซ ๐ฎ๐ฌ๐ž. ๐‹๐ฒ๐ซ๐ข๐œ๐ฌ ๐š๐ง๐ ๐ฆ๐ฎ๐ฌ๐ข๐œ ๐›๐ž๐ฅ๐จ๐ง๐ ๐ฌ ๐ญ๐จ ๐ญ๐ก๐ž ๐ซ๐ข๐ ๐ก๐ญ๐Ÿ๐ฎ๐ฅ ๐จ๐ฐ๐ง๐ž๐ซ๐ฌ.

12/05/2026
11/05/2026

๐—ฃ๐—ข๐—ช๐—˜๐—ฅ ๐—•๐—Ÿ๐—ข๐—– ๐—™๐—œ๐—Ÿ๐—˜๐—ฆ ๐—ฅ๐—˜๐—ฆ๐—ข๐—Ÿ๐—จ๐—ง๐—œ๐—ข๐—ก ๐—ฆ๐—˜๐—˜๐—ž๐—œ๐—ก๐—š ๐—ฅ๐—˜๐—ฉ๐—œ๐—˜๐—ช ๐—ข๐—ก ๐—š๐—˜๐—”-๐—”๐—Ÿ๐—Ÿ ๐—–๐—›๐—”๐—ฅ๐—š๐—˜๐—ฆ, ๐—˜๐—ฅ๐—– ๐—›๐—”๐—Ÿ๐—ง๐—ฆ ๐—š๐—ฅ๐—˜๐—˜๐—ก ๐—˜๐—ก๐—˜๐—ฅ๐—š๐—ฌ ๐—™๐—˜๐—˜๐—ฆ

Noong May 4, 2026, naghain sina PhilRECA Party-List Rep. Presley C. De Jesus at APEC Party-List Rep. Sergio C. Dagooc ng House Resolution No. 978 upang imbestigahan ang legality, validity, at constitutionality ng Green Energy Auction Allowance (GEA-All) na ipinapataw sa mga konsyumer sa ilalim ng ERC Resolution No. 06, Series of 2025.

Kasunod ng paghahain ng nasabing resolusyon, naglabas kaagad noong May 08, 2026 ang Energy Regulatory Commission (ERC) ng hakbang na pansamantalang ipahinto ang koleksyon ng GEA-All habang sinusuri ang mga isyung kaugnay ng implementasyon nito.

Hindi tutol ang Power Bloc sa renewable energy. Gayunman, naniniwala ito na ang pagsusulong ng malinis na enerhiya sa bansa ay dapat nakabatay sa malinaw na legal at konstitusyunal na basehan, lalo na kung may kaakibat itong dagdag-singil na direktang makaaapekto sa bawat pamilyang Pilipino.

Sa ilalim ng House Resolution No. 978, layunin nitong suriin kung ang naturang charge ay may sapat na statutory basis at kung naaayon ito sa mga kapangyarihang ipinagkaloob ng batas sa ERC. Para sa Power Bloc, mahalagang matiyak na ang anumang bagong obligasyong pinansyal na ipapataw sa consumers ay dumaan sa wastong proseso at mahigpit na pagbubusisi ng Kongreso.

Sa huli, sinusuportahan ng Power Bloc ang pansamantalang paghinto ng ERC sa koleksyon ng GEA-All, subalit hindi dapat dito ito magtatapos. Sa huli, patuloy nating babantayan ang isyung ito para masig**o natin ang abot-kayang kuryente, transparency sa paniningil, at proteksyon sa kapakanan ng bawat konsyumer, lalo na sa panahon ng patuloy na pagtaas ng presyo ng mga pangunahing bilihin at serbisyo.

10/05/2026

Ngayong Motherโ€™s Day, binibigyang-pugay natin ang lahat ng nanay at mga tumatayong Ilaw ng Tahanan na araw-araw na nagsisilbing lakas, gabay, at inspirasyon ng bawat pamilyang Pilipino.

Sa likod ng bawat tagumpay ay isang inang walang sawang nagsasakripisyo, gumigising nang maaga, nagsisikap kahit pagod, at patuloy na lumalaban para mabigyan ng mas magandang kinabukasan ang kanilang mga anak.

Kayo ang unang g**o ng pagmamahal, tiyaga, at pag-asa. Sa bawat yakap, payo, at tahimik na pag-aaruga, nabubuo ang mas matatag na tahanan at mas maunlad na komunidad.

Ngayong araw, iparamdam natin sa ating mga nanay kung gaano sila kahalaga. Sabihin natin ang mga salitang madalas nating nakakalimutang banggitin: โ€œSalamat, Ma. Mahal na mahal ka namin.โ€

Mula sa APEC Party-List, isang taos-pusong pagbati ng Happy Motherโ€™s Day sa lahat ng Ilaw ng Tahanan!

NOTICE OF DEFERMENT from the National Grid Corporation of the PhilippinesPlease be informed that the scheduled power int...
08/05/2026

NOTICE OF DEFERMENT from the National Grid Corporation of the Philippines

Please be informed that the scheduled power interruption of the NGCP on MAY 9, 2026 affecting LIANGA, SAN AGUSTIN, MARIHATAG, CAGWAIT, BAYABAS, SAN MIGUEL, TAGO, CORTES, AND TANDAG CITY is POSTPONED to MAY 16, 2026.

Thank you very much.

Deferred Power Interruption in Tandag City and Parts of Surigao del Sur

The scheduled power interruption on 09 May 2026, Saturday, affecting SURSECO 2 ( Surseco 2, Inc. ) (Lianga, Cagwait, and Tandag Substations) for the maintenance activities of San Franciscoโ€“Tandag 69kV Line, is deferred per request of Tandag Chamber of Commerce and Industry.

The new schedule is 16 May 2026, Saturday, 6:00 AM โ€“ 6:00 PM.

Thank you for your patience and understanding.

Address

Tandag
8300

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Telephone

(086) 211 3553

Alerts

Be the first to know and let us send you an email when Surseco 2, Inc. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Surseco 2, Inc.:

Share

Category