Engineering review of industrial and commercial building work, Construction supervision of industrial and different type of Light gauge and Pre-engineered buildings.Preparing bill of quantities, estimates, and Project monitoring. Coordination between Project office, Consultants & Client offices and also involved in various activities related to the field of civil engineering.

Component of Development Budget for a 3 Star*** Hotel.➡ Dry Cost:• Material Cost• Manpower Cost• Equipment CostDry cost ...
09/12/2023

Component of Development Budget for a 3 Star*** Hotel.

➡ Dry Cost:
• Material Cost
• Manpower Cost
• Equipment Cost
Dry cost varies from 55 ~ 65 % of the development cost.

➡ Indirect Cost:
• Supervision Cost
• PMV Cost
• Site Facilities
• Insurance & Bonds
Indirect Cost varies from 10 ~ 20% of the development cost.

➡ Construction Contractor Mark-up:
• Profit Margin
• OH
• Risk
Mark-up ranges 8 ~ 15% of the development cost.

⭕ Hard Cost:
= Dry Cost + Indirect Cost + Mark-up

➡ Soft Cost:
• Design Cost
• PMT
• Consultancies
• Marketing
Soft cost ranges from 5 ~ 8% of the development cost.

⭕ CapEx Cost:
= Hard Cost + Soft Cost

➡ Management Reserve:
• Contingencies
• Inflation
Management reserve varies from 5 ~7% of development cost.

⭕ Development Cost:
= CapEx Cost + Management Reserve.

Development Cost is the total of all costs incurred in the completion of a development.

19/11/2023

Address

Pcsir Phase 2 Community Center Office No. 1
Lahore
44000

Telephone

+923484270301

Website

Alerts

Be the first to know and let us send you an email when Estimation & Costing posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Estimation & Costing:

Share