10/01/2026
We’re documenting the current stage of construction at Gardens of Eden and sharing key updates across all areas of the project ↓
🔝 COMPLETED
Eden Residences
✓ Exterior and interior masonry walls completed in Buildings C and E
✓ Exterior and interior masonry walls completed up to the third floor in Building G
✓ Exterior and interior masonry walls completed up to the second floor in Buildings D and F
✓ Installation of sanitary plumbing systems and electrical conduits completed on the first floors of Buildings G, E, F, C, and D
✓ Basement slab completed in Building B
Park Residences
✓ Basement car parking slab completed in Building H
✓ Structural works and preparation of basement parking slabs ongoing in Buildings M, L, J, and K
✓ Structural elements completed up to the basement car parking slab in Building I
✓ Test piling works commenced at Lake Residences
🔛 IN PROGRESS
Eden Residences
✓ Installation of sanitary plumbing systems and electrical conduits started on the second floors of Buildings G, E, F, C, and D
✓ Construction of walls and columns underway between the basement level and the first-floor slab in Building B
✓ Installation of foundation piles started for Building A and the Phase 1 lobby
Park Residences
✓ Basement parking slabs under construction in Buildings K, J, M, and L
✓ Construction of basement parking walls and columns ongoing in Building H
✓ Waterproofing works underway on the roof and balconies of the Sales Gallery
✓ Columns and an intermediate reinforced concrete slab under construction in the Sales Gallery car park
✓ Test piles installed at Lake Residences 1 and 2
🔜 PLANS
Eden Residences
✓ Complete exterior and interior masonry walls in all five buildings
✓ Complete installation of sanitary plumbing systems and electrical conduits up to the third floor
✓ Complete wall plastering works up to the second floor
✓ Complete floor screeding works up to the second floor
✓ Advance structural works in Building B up to the second-floor slab
✓ Continue installation of foundation piles for Building A and the Phase 1 lobby
Park Residences
✓ Complete basement parking slab construction in Building I
✓ Continue construction of basement walls and columns in Buildings M, L, J, and K
✓ Construct the first-floor slab in Building H
✓ Complete construction of the Sales Gallery car park
✓ Carry out dynamic load testing of piles at Lake Residences
Construction continues at a steady, well-coordinated pace in line with the approved development plan. The team is moving forward step by step, shaping the resort as originally envisioned.
Thank you for following the progress of Gardens of Eden