Kk trust builders group

Kk trust builders group Kk trust builders group uganda limited

From kk trust builders      Simple shop      ACCOUNTABILITY ( first phase)     ( ground floor and first floor)         M...
31/03/2026

From kk trust builders
Simple shop
ACCOUNTABILITY
( first phase)
( ground floor and first floor)
Material needed
1iron bars
T12 ( bases)×38,000 #608,000
T16 ( columns)×68,000 #1,632,000
2.ring wires @30( r8)×13,000 #390,000
3.baing wires ×200,000 #400,000
4.nails of all size #150,000
5.kilundu @ 80peaces ×7,000 #560,000
6.kalitunsi 30poles ×4,000 #120,000
7.dpm @ 1roles×230,0000 #230,000
Athers
8.bricks @ 4,0000 each trip costs 250,000 #1,000,000
9.hollow blocks @1495×1800 #2,691,000
10.omusenyu
Lake sand of forward box ×500,000 #1,500,000
Plaster sand of forward box×500,000 #1,500,000
11.soft stone of 4×250,000 #1,000,000
12.cement @ 55bags ×33,000( Semi2) #1,815,000
13.hoop alron ×40,000 #120,000
14.transport costs/micelinious costs # 500,000

Total =14,216,000
Labour = ...................

SECOND PHASE
( SLAB AND SECOND FLOOR UP TO WALLPLATE)

MATERIAL REQUIRED
1.iron bars
T16 (main beams)×68,000 #1,292,000
T16 ( flashing beams)×68,000 #816,000
T16 @ 16bars( columns)×68,000 #1,088,000
T12 @ 28 ( wallplate beams)×38,000 #1,064,000
T12@15( ribs)×38,000 #570,000
T12 @ 18bars( laders)×38,000 #684,000
2.ring wires @ 120peaces×13,000 #1,560,000
3.baing wires @ 3roles ×150,000 #450,000
4.kilundu @200×7500 #1,500,000
5.kalitunsi ×4,000 #720,000
6.nalis of all size #200,000
7.brc @( A66)1role×450,000
8.dpc ×3,000 #75,000
9.maxpand pan@250( 6inch)×4500 #1,125,000
10.piping electricity.
Material =300,000

Athers
11.hollow blocks @2,000 ×1800 #3,600,000
12.omusenyu
Lake sand of forward box×500,000 #1,500,000
Plaster sand of forward box×500,000 #1,000,000
13.soft stone of forward Flat ×250,000 #1,000,000
14.cement (semi 2)×33,000 #1,980,000
16.mechanical works/micelinious/transportation # 500,000

Total amount =21,474,000
Labour = ...................

Free of charge consultation
What app 0708282239

23/03/2026

FROM KK TRUST BUILDERS GROUP UGANDA

Maya project

LIMITED.
3.UNITS ACCOUNTABILITY ( SELF CONTAINED)
OWNER .................
ACCOUNTABILITY
( FROM FOUNDATION UPTO WALLPLATE)

1.BLOCKS @ 35,000 each trip costs 270,000 each trip consists of 1000 bricks ×35trips #9.450,000

2.cement (tororo semi 2)×32,000 #8,000,000
3.omusenyu
Lake sand of snaltruck ×1,800,000 #3,600,000
Plaster sand of snaltruck #1,700,000
4.kalitunsi ×5,000 #750,000
5.kiludu @ 150peaces ×8,000 #1,200,000
6.bottoms ×6,000 #210,000
7.nails
Inch 5= 10kgs×5500 #55,000
3= 15kgs×5500 #82500
4= 15kgs×5500 #82500
2½= 7kgs×6500 #45500
8.hoop alron ×40,000 #40,000
9.10 lron bars
T12 = 50bars×38,000 #1,900,000
T10=40bars ×25,000 #1,000,000
T16=20bars×68,000 #1,360,000
10.baing wires ×150,000 #300,000
11.ring wires ( r7)×10,000 #450,000
12.soft stones of flat ×250,000 #500,000
11,sisal @ 6roles×7,000 #42000
13plain sheets ×12,000 #144,000
14.transport #200,000
15.micelinious costs #2,000,000 ( watter billies. Site clearing

Total material = 33,111,500

Labour required = .................... negotiable

FROM KK TRUST BUILDERS GROUP             UGANDA LIMITED     HIDDEN ROOFED STRUCTURE    OWNERS MR.  RAccountability  From...
17/12/2025

FROM KK TRUST BUILDERS GROUP
UGANDA LIMITED

HIDDEN ROOFED STRUCTURE
OWNERS MR. R

Accountability From foundation up to the wallplate

Material needed
1.blocks @ 10,000 each trip costs 250,000 means 10trips×250,000 #2,500,000
2.hollow blocks @3,000 each block costs 1800 #5,400,000
2.omusenyu
Lake sand @ 3trips of forward box ×550,000 #1,650,000
Plaster sand of forward box 500,000 #1,000,000
4.soft stones of forward flat #250,000
5.cement 120bags(tororo)×32,000 #3,840,000
6.dpc ×3,000 #105,000
7.kalitunsi ×4,000 #360,000
8.iron bars
Y12 @ 35pieces×38,000 #1,330,000
Y10@ 20peaces ×25,000 #500,000
9.baing wires ×75,000 #150,000
10.ring wires @ ( r7) 35peaces ×13,000 #455,000
11.sisal ×7,000 #28,000
12.hopiron @ 5roles×45,000 #225,000
13.plain sheets ×15,000 #180,000
14. Nails
Inch4= 10kgs×5500 #55000
5=5kgs×5500 #27,500
3=10kgs×5500 #55,000
2⅓=6kgs×7,000 #42,000
14. Kilundu @ 80pieces×8,000 #640,000
15.bottomes ×6,000 #120,000
16 transport # 150,000 ( like cement etc)
11.micelinious #1,500,000

Total amount =20,562,000

Labour = ......................

Thanks for the opportunities

From kk trust builders 👷‍♀️ Uganda Limited                   Limited. ACCOUNTABILITY         Busukuma project       Owne...
17/12/2025

From kk trust builders 👷‍♀️ Uganda Limited
Limited.
ACCOUNTABILITY
Busukuma project
Owner ..................
.......

Accountability From foundation up to the wallplate

Material needed
1.blocks @ 22,000 each trip costs 250,000 means 22trips×250,000 #5,500,000
2.omusenyu
Lake sand of snaltruck ( yellow sand) #1,900,000
Plaster sand of snaltruck #1,700,000
3.soft stones of forward flat #250,000
4.cement 120bags(tororo)×32,000 #3,840,000
5.dpc ×3,000 #105,000
6.kalitunsi ×4,000 #360,000
7.iron bars
Y12 @ 35pieces×38,000 #1,330,000
Y10@ 20peaces ×25,000 #500,000
8.baing wires ×75,000 #150,000
9.ring wires @ ( r7) 35peaces ×13,000 #455,000
10.sisal ×7,000 #28,000
11.hopiron @ 5roles×45,000 #225,000
12.plain sheets ×15,000 #180,000
13. Nails
Inch4= 10kgs×5500 #55000
5=5kgs×5500 #27,500
3=10kgs×5500 #55,000
2⅓=6kgs×7,000 #42,000
14. Kilundu @ 60pieces×8,000 #480,000
15.bottomes ×6,000 #120,000
16 transport # 150,000 ( like cement etc)
11.micelinious #1,500,000

Total amount =18,952,500

Labour = ..........................

Thanks for the opportunities

From kk trust builders group Uganda                  Limited. First phase     ( PLAN DEVOLVING AND PLAN APPROVAL)       ...
17/12/2025

From kk trust builders group Uganda
Limited.

First phase
( PLAN DEVOLVING AND PLAN APPROVAL)

Plan developing =1.000,000
Plan Aprovals = 1,500,000


3.bedroom house
Owner .............. ...........

3 bedroomed house Accountability From foundation up to the wallplate
(Using normal bricks)

MATERIAL REQUIRED
1.blocks @ 15,000 each trip costs 250,000×12trips #3,750,000
2.hollow blocks @33,000 each block costs 18,000 #5,940,000

2.cement @ 150 bags(tororo)×32,000 #4,800,000
3.omusenyu
Lake sand @ 1trip of snaltruck( white sand) #2,200,000
Plaster sand of snal truck #1,700,000
4.soft stones of forward flat #250,000
of elif #150,000
5.iron bars
T12 @ 37pieces ×40,000 #1,480,000
T16@ 25peaces ×35,000 #700,000
6.bainig wires @ 1role ×150,000 #150,000
7.ring wires @( r7)×30peaces ×13,000 #390,000
8.kilundu ×8,000 #720,000
9.nails
Inch4 =15kgs×5500 #82500
3=15kgs×5500 #82500
1½=5kgs×6500 #32500
10.plain sheets ×70,000 #140,000
11.dpc ×3000 #45,000
12.sisal ×7,000 #28000
13.bottoms @ 20peaces ( 6inch)×8000 #160,000
16.hoop alron ×45,000 #315,000
17.transport costs #200,000
18micelinious costs #1,500,000 ( water billies)

Total amount = 24,733,000

Labour required = ..................... negotiable

Grand total = .....................

Tools needed at the site is an offer from the company

From kk trust builders group Uganda                      Limited.     Bukerere Appartment Project     It's plan and acco...
25/01/2025

From kk trust builders group Uganda
Limited.
Bukerere Appartment Project
It's plan and accountability is out
Vist us through What's
0708282239
Call direct on 0708282239

Asalam alaikum walahumatulahi wabalakatuh

KK TRUST BUILDERS GROUP UGANDA LIMITED proudly updates that the Wakiso project is on track. We appreciate the trust plac...
01/10/2024

KK TRUST BUILDERS GROUP UGANDA LIMITED proudly updates that the Wakiso project is on track. We appreciate the trust placed in us by our clients in Uganda and globally. For project inquiries, kindly reach us on 0708282239 via WhatsApp or call 0773753640 at no cost. We value your partnership. Asalam alaikum walahumatulahi wabalakatuh.

Address

Lubugumu Off Entebbe Road
Kampala

Telephone

+256708282239

Website

Alerts

Be the first to know and let us send you an email when Kk trust builders group posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Kk trust builders group:

Share