From kk trust builders
Simple shop
ACCOUNTABILITY
( first phase)
( ground floor and first floor)
Material needed
1iron bars
T12 ( bases)×38,000 #608,000
T16 ( columns)×68,000 #1,632,000
2.ring wires @30( r8)×13,000 #390,000
3.baing wires ×200,000 #400,000
4.nails of all size #150,000
5.kilundu @ 80peaces ×7,000 #560,000
6.kalitunsi 30poles ×4,000 #120,000
7.dpm @ 1roles×230,0000 #230,000
Athers
8.bricks @ 4,0000 each trip costs 250,000 #1,000,000
9.hollow blocks @1495×1800 #2,691,000
10.omusenyu
Lake sand of forward box ×500,000 #1,500,000
Plaster sand of forward box×500,000 #1,500,000
11.soft stone of 4×250,000 #1,000,000
12.cement @ 55bags ×33,000( Semi2) #1,815,000
13.hoop alron ×40,000 #120,000
14.transport costs/micelinious costs # 500,000
Total =14,216,000
Labour = ...................
SECOND PHASE
( SLAB AND SECOND FLOOR UP TO WALLPLATE)
MATERIAL REQUIRED
1.iron bars
T16 (main beams)×68,000 #1,292,000
T16 ( flashing beams)×68,000 #816,000
T16 @ 16bars( columns)×68,000 #1,088,000
T12 @ 28 ( wallplate beams)×38,000 #1,064,000
T12@15( ribs)×38,000 #570,000
T12 @ 18bars( laders)×38,000 #684,000
2.ring wires @ 120peaces×13,000 #1,560,000
3.baing wires @ 3roles ×150,000 #450,000
4.kilundu @200×7500 #1,500,000
5.kalitunsi ×4,000 #720,000
6.nalis of all size #200,000
7.brc @( A66)1role×450,000
8.dpc ×3,000 #75,000
9.maxpand pan@250( 6inch)×4500 #1,125,000
10.piping electricity.
Material =300,000
Athers
11.hollow blocks @2,000 ×1800 #3,600,000
12.omusenyu
Lake sand of forward box×500,000 #1,500,000
Plaster sand of forward box×500,000 #1,000,000
13.soft stone of forward Flat ×250,000 #1,000,000
14.cement (semi 2)×33,000 #1,980,000
16.mechanical works/micelinious/transportation # 500,000
Total amount =21,474,000