06/12/2025
One year ago π, work at the South Brooklyn Marine Terminal ( ) began π¨ποΈ. So many major accomplishments have happened in the last year including:
π·π·π½ββοΈ π·πΎββοΈ Over 2,000 people have worked at the site.
π§ π οΈ Over 50% of the work has been completed, including the demolition of existing buildings, the delivery of important substation components, completion of over 2,000 piling sections for the crane pads, installing new utilities, and of the Operations and Maintenance building, which is now halfway to completion.
π π€ Engagement with local and national , injecting hundreds of millions of dollars into the .
Check out how much progress has been made in just a year, as we prepare for the port to go operational in 2026.
Local #3 IBEW I.U.O.E. Local 14-14b NYC New York City District Council of Carpenters New York City Central Labor Council, AFL-CIO Greater New York Laborers-Employers Cooperation & Education Trust North America's Building Trades Unions Teamsters Laborers Local 79 - New York City