08/15/2026
We wrapped up the biggest job of the year so far- an 18,000 sq ft metalizing job on 15 steel girders that are heading to Alaska. We blasted all the surfaces to an SSPC-SP5 surface, then applied 10 mils of pure zinc with our arc spray metalizing machine. It took us about 4 weeks to complete this project from start to finish.