11/15/2025
The team had a huge week of production at the Big Bear Express project in front of Panorama Village. Lots of coordination and planning for all the moving parts. We pumped roughly 750 yards of between the retail building and the retention pond footing for the 10’ vertical wall. The underground plumbing for the second building which is a truck stop is completed and ready for backfill. We will continue with the storm piping and utilities as this project has roughly 3,000 ft of underground retention system.