Another successful project completed by the Golden Ratio team at PDX Airport as part of the SEDS CBIS Inline Project.
After arriving at PDX Airport, the team coordinated with project leadership and airport stakeholders to review the planned activities and access requirements. Once TSA es**rt access was secured, the crew conducted a detailed safety and operational briefing covering the scope of work, project objectives, potential hazards, equipment handling procedures, and ex*****on strategy. With all personnel aligned and safety measures in place, the team began the decommissioning, inventory, disposition, and shipment preparation activities.
With safety and coordination leading the effort, the team systematically identified, inventoried, decommissioned, packaged, crated, and dispositioned equipment throughout the work area. The scope included:
β
27 SVS units and 2 PVS units decommissioned, inventoried, packaged, crated, and staged for return shipment to the Transportation Security Administration Logistics Center (TSALC) in Coppell, Texas
β
Additional equipment packaged and crated for shipment to the TSALC, including:
β’ (1) CT-80 Infeed Conveyor
β’ (3) Conveyor Pedestal Kits
β’ (1) Scanner Pedestal Kit
β’ (1) CT-80 XL Tunnel Pedestal Kit
β
31 monitors, 29 keyboards, 29 mice, and 27 UPS units removed from service and turned over to our rigging partner, Integrity Machinery Moving, for local disposal in accordance with project requirements and site disposition procedures
The team maintained complete accountability of all project assets throughout the operation, ensuring every item was properly inventoried, packaged, and prepared for transport. Once crating activities were complete, the equipment was staged for shipment back to the Transportation Security Administration Logistics Center (TSALC) in Coppell, Texas, where it will be processed and made available to support future TSA screening operations nationwide.
Special thanks to our project partners who helped make this effort a success:
πΉ Integrity Machinery Moving β Local rigging support and disposition services
πΉ MEI Industrial Solutions β Professional crating and packaging services, ensuring all equipment was properly protected and prepared for transport
πΉ Omni Logistics β Providing safe, reliable, and on-time transportation services to return the equipment to the TSALC
The project progressed smoothly from start to finish with no delays, safety incidents, or operational disruptions. Through strong planning, communication, and teamwork, the crew successfully executed the mission while maintaining the highest standards of safety and professionalism.
Another outstanding example of Golden Ratio personnel delivering results and supporting the modernization and sustainment of critical airport security infrastructure.