07/01/2026
132 / 134 Sycamore Road Roslindale Ma
Site Work an Utilities
Completion date: 6/30/26
Another project successfully completed and added to the growing portfolio.
This was one of the tightest jobs we’ve tackled, with only 10 feet of clearance between neighboring homes and property lines, leaving very little room to work with equipment. It took a lot of planning and patience, but the crew got it done safely and efficiently. Proud of another quality project in the books.
500 linear feet of 6” SDR drain pipe
(2) 6” sewer services tapped at the main 11 feet deep
(2) 1” domestic water services tapped at the main
(2) 6” drain overflows tapped into a 48” concrete encased drain main
(8) cultec units
(2) concrete catch basins
And over 500 yards of material hauled out as well as over 500 yards of good material hauled back in.