09/07/2026
450 squares. 3.5 days. 🔥
But the roof was only part of the project.
Along the way, our team completed structural repairs to 5 trusses with a 1.5” drop, removed 3 skylights, installed 5 squares of TPO roofing, and installed 6 squares of 8.5” James Hardie lap siding — all while completing the interior and exterior scope of this project in just 7 days total.
What does it take to pull off an operation like this?
• 6 tractor-trailer deliveries of material
• 6 dumpsters
• 12 hotel rooms
• 5 company trucks
• 3 trailers
• 1 fifteen-passenger van
• And a whole lot of water, Gatorade, electrolytes, long days, and teamwork.
We faced some unforeseen challenges along the way, as you do on projects of this size, but our guys handled every one of them and kept moving forward.
I couldn’t be more proud of this crew.
From mobilization to the final details, this was a massive team effort — and I couldn’t be happier with the finished product.
450 squares. 3.5 days. Full project. 7 days.
That’s what a great crew, good planning, and a whole lot of hard work can accomplish.