A remodel timeline is easier to plan backward.
Start with the month you want to be done: before the holidays, before a graduation party, before a summer at the lake. Subtract construction time for your scope, which your builder should be able to give you in weeks. Then subtract three to five months of preconstruction for design, selections, trade pricing, and permits.
What's left is the month design needs to start. For a spring 2027 start, that month is this fall or winter.
The first step is a no-obligation site assessment and design proposal: a scope of work and a potential cost breakdown.