Rehabilitation work will begin on Road Bridge on August 17 for ~ 7 months. Work will run Mon-Fri 8:30 am - 3:30 pm (excluding holidays). Traffic control measures will be in place throughout the project:
* Mid-August: One lane open to alternating traffic
* Late August - Late December: Bridge closure 24 hours/day, 7 days a week
* Early January - Mid February - One lane open to alternating traffic
An on-demand shuttle will be provided by TheBus for the Valley View Dr. community,
operating between Valley View Dr. and Kamehameha Shopping Center during the
Late August - Late December portion of the project.