03/03/2026
Construction at McHenry Commons in McHenry, IL continues to advance steadily as the project progresses toward its June 2026 turnover.
Exterior work is substantially complete, with siding and masonry installations finalized. Balcony railings are scheduled to arrive and will be installed over the next month, and elevator installation is the next major milestone on site.
Interior buildout is progressing sequentially by floor. On the third floor, cabinet installation and flooring are underway, with all bathroom tile completed and LVP currently being installed. The second floor is nearing completion of taping and texturing, with cabinetry scheduled for installation this month. On the first floor, interior wall insulation is complete and drywall hanging is in progress, maintaining strong momentum throughout the building.