04/10/2026
Our Trenchless Division is off to a strong start on this challenging project in Central New Jersey bypassing sewer flows upwards of 2,750 GPM so that crews can rehabilitate multiple sections of 36-Inch Diameter Sewer totaling 2,200 LF. Working in a tight wooded easement with one way in and out and setting up pumps in the back yard of a property owner required additional planning and a high level of detail to execute successfully.
Bypass Foreman Bill Mogan and his crew are handling the following tasks:
1. Build Stone Access Road
2. Bypass Pumps Placement
3. Fusing of 2,500 LF of 12" HDPE Pipe
4. Freshwater pressure test of all piping to confirm no leaks
5. Set bypass Plugs and monitor
Cured In Place Pipe Foreman Ben Felshaw and his crew are handling the following tasks:
1. Clean and Inspect Sewer Lines
2. Installation of the Cured In Place Pipe Liners.