08/21/2026
We’ve seen good progress in recent weeks on the new, 9,000-square-foot building for Seal Stone Properties LLC in Kechi.
Much of the exterior finish on the front of the building and exterior concrete has been completed. However, some work still remains.
Work continues on the inside of the building as well, with flooring installation and final painting among the projects nearing completion.
The project started ramping up in January as the site was prepared for the building. The concrete pad was poured in early February. The building was then erected, sheeted and roofed in the weeks that followed.
Check out our updated video that shows the months-long transformation of the job site.