Progress Update | Monomoy Regional Middle School.
A full envelope rebuild on a 120,000-square-foot school building. We took the exterior down to the structure to inspect every cavity before closing it back up. It’s the only way to understand moisture history and specific areas to address.
Project: Exterior Improvements to includes new plywood sheathing, windows, pvc trim and hardie shingle impressions. Upgraded waterproofing and flashings. Currently removing all siding, trim, windows and plywood sheathing in a multiple phased approach to minimize impact on the students and staff. Correcting moisture, water, mold and any damage to framing or insulation. From there, it’s a coordinated enclosure sequence: new sheathing, waterproofing, v***r barriers, windows, and finishes.
On site now:
- Exterior strip-down and cavity inspections in progress
- Plywood replacement in progress
- Waterproofing and v***r barriers going on in sequence
- Window preparation and installation underway
-Siding and trim crews onsite and installing as per details and manufactures warranty standards
Coming up:
-Exterior close-in and finish carpentry
-Final flashing and trim details
Multiple trades working in rhythm, each one staged so the next can start clean.
Shoutout to Emmanuel Construction, Kapiloff Glass, Contracting Specialists Inc., Banner Environmental Services Inc., and for the continued coordination and quality work on site.