Earlier this summer, our team in South Florida completed the mat foundation placement at the St. Regis Residences Sunny Isles project in Miami.
Over 19 continuous hours, more than 150 Baker co-workers placed 8,262 cubic yards of concrete across an 18,975-square-foot mat foundation. The operation required three shifts, 145 concrete trucks in rotation, five concrete pumps, and months of planning that began during preconstruction.
Located approximately 25 feet below the water table and adjacent to the beach, the foundation presented tight logistics and complex site conditions. Thanks to detailed planning and close coordination among Baker, the client, and trade partners, the team executed the foundation placement safely and successfully.