We recently started another bathroom remodel in Murphy, NC and wanted to show you a little behind the scenes of our process!
Before any work begins, we always take our time to prepare the home as best as possible. We like using RAM board to protect all flooring, and lay it out along the path we intend to use in and out of the home. Then we put up the ZipWall to create a dust barrier, as demo in particular kicks up a LOT of dust.
Once set up, demolition can begin! For this project everything had to go! We usually start with removing the tub structure, and then work out way around the room. For this bathroom we removed the toilet, vanity, wall miror, and closet. Flooring is usually the last to go once all other pieces are removed.
With demo complete, the next step is prep and rough in! We can’t wait to share more about this project. Be sure to follow along over the next few weeks to see the finished transformation as well.