Framers kicked some ass. We loaded roof on Wednesday. By Saturday roof is stacked and sheeted. Fascia and soffit done. W...
08/18/2026

Framers kicked some ass. We loaded roof on Wednesday. By Saturday roof is stacked and sheeted. Fascia and soffit done. We are in a fire zone so we have to have closed eaves.

Crane day last week. Got the trusses and plywood loaded on roof. Framers are there today finishing up the roof. We are g...
08/15/2026

Crane day last week. Got the trusses and plywood loaded on roof. Framers are there today finishing up the roof. We are going to get started on plumbing and electricaal next week now that the roof is finished up. Scaffolding went up Friday to finish second floor shear and to set windows.

We built this new entry for a client in wine country. We carried the vault all the way into the entry and added a new tr...
07/09/2026

We built this new entry for a client in wine country. We carried the vault all the way into the entry and added a new transom window over the existing front door.

A couple pictures from the San Clemente project. Second floor is plated and being framed tomorrow and Monday. The are to...
06/26/2026

A couple pictures from the San Clemente project. Second floor is plated and being framed tomorrow and Monday. The are to left on Second picture is going to be a large 640 SF deck. Half of it will be covered. There will also be a small deck off the master bedroom.

First floor framing wrapping up today. Plumb and line this afternoon. Starting second floor framing Monday. Steel beam b...
06/12/2026

First floor framing wrapping up today. Plumb and line this afternoon. Starting second floor framing Monday. Steel beam being installed on Thursday.

We finished up foundation on San Clemente project today. Strip forms and saw cut tomorrow. Starting Framing next Tuesday...
06/04/2026

We finished up foundation on San Clemente project today. Strip forms and saw cut tomorrow. Starting Framing next Tuesday. Ended up being 83 yards or concrete

First truck of the day.
06/02/2026

First truck of the day.

Project in San Clemente is coming along. Tons of rebar in this foundation. We just need to add dobies to the deck rebar ...
05/22/2026

Project in San Clemente is coming along. Tons of rebar in this foundation. We just need to add dobies to the deck rebar and add some diagonal stakes to forms. The forms took a beating from the helical pier contractor. We basically had to reset everything. Inspection and pour next week. Probably 80-90 yards.

Footings are all dug on San Clemente project. We got out first lumber lumber drop from Ganahl Lumber Company today. Form...
04/15/2026

Footings are all dug on San Clemente project. We got out first lumber lumber drop from Ganahl Lumber Company today. Form boards, Hardy templates and bolts and a roll or 15 mil Stego. Underground plumbing starting next week.

Demo is complete on San Clemente remodel. Working on grading the pad this week. Starting footings next week so helical p...
04/03/2026

Demo is complete on San Clemente remodel. Working on grading the pad this week. Starting footings next week so helical pier contractor can get their work done. It is a busy foundation with both slab and raised foundation and 8 Hardy panels on first floor.

Address

Murrieta, CA
92562

Alerts

Be the first to know and let us send you an email when Grattan Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Grattan Construction:

Shortcuts

Share