Grattan Construction

Directions Website Contact the business

Grattan Construction Home improvement and remodel specialist. New home construction from design to finish.

We got decks and roof dried in on San Clemente project. Waiting on a couple windows and front door so we can start wrapp...
10/16/2026

We got decks and roof dried in on San Clemente project. Waiting on a couple windows and front door so we can start wrapping house. That fire on Pendleton is getting closer. Freeway is shut down.

We finished up this master bathrrom remodel last month in Morgan Hill. A big update on the orginal bathroom. All new sho...
10/15/2026

We finished up this master bathrrom remodel last month in Morgan Hill. A big update on the orginal bathroom. All new shower, tub, cabinets, countertops, mirrors, and floor tile. Bathroom design and material selection by Designed with Grace & Joy. Lindsey Machado is great to work with.

We finished this loft project up a couple weeks ago for a client in Redhawk. It required a steel beam to span the openin...
10/15/2026

We finished this loft project up a couple weeks ago for a client in Redhawk. It required a steel beam to span the opening. Ended up with a nice size bedroom and closet accessed by a short hallway.

Framers kicked some ass. We loaded roof on Wednesday. By Saturday roof is stacked and sheeted. Fascia and soffit done. W...
08/18/2026

Framers kicked some ass. We loaded roof on Wednesday. By Saturday roof is stacked and sheeted. Fascia and soffit done. We are in a fire zone so we have to have closed eaves.

Crane day last week. Got the trusses and plywood loaded on roof. Framers are there today finishing up the roof. We are g...
08/15/2026

Crane day last week. Got the trusses and plywood loaded on roof. Framers are there today finishing up the roof. We are going to get started on plumbing and electricaal next week now that the roof is finished up. Scaffolding went up Friday to finish second floor shear and to set windows.

We built this new entry for a client in w**e country. We carried the vault all the way into the entry and added a new tr...
07/09/2026

We built this new entry for a client in w**e country. We carried the vault all the way into the entry and added a new transom window over the existing front door.

A couple pictures from the San Clemente project. Second floor is plated and being framed tomorrow and Monday. The are to...
06/26/2026

A couple pictures from the San Clemente project. Second floor is plated and being framed tomorrow and Monday. The are to left on Second picture is going to be a large 640 SF deck. Half of it will be covered. There will also be a small deck off the master bedroom.

First floor framing wrapping up today. Plumb and line this afternoon. Starting second floor framing Monday. Steel beam b...
06/12/2026

First floor framing wrapping up today. Plumb and line this afternoon. Starting second floor framing Monday. Steel beam being installed on Thursday.

We finished up foundation on San Clemente project today. Strip forms and saw cut tomorrow. Starting Framing next Tuesday...
06/04/2026

We finished up foundation on San Clemente project today. Strip forms and saw cut tomorrow. Starting Framing next Tuesday. Ended up being 83 yards or concrete

First truck of the day.
06/02/2026

First truck of the day.

Address

Murrieta, CA
92562

Alerts

Be the first to know and let us send you an email when Grattan Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Grattan Construction:

Shortcuts

Share