05/25/2026
Excited to share our work on the City of Los Angeles' new Advanced Water Purification Facility (AWPF) at the Donald C. Tillman Advanced Water Reclamation Plant in Van Nuys. This half-acre facility, with advanced water purification technologies, must be completed before the 2028 Olympics to support California’s water reuse goals on the world stage.
Delivered under a progressive design-build contract with Jacobs, the project required us to begin construction while design work was still underway. Our team is responsible for installing critical civil utility and process piping — some as large as 48 inches in diameter and set 22 feet deep — within an active, highly congested treatment plant.