06/03/2025
We are excited to be a part of the new SR 18 interchange project. We had crews out this weekend doing stamped concrete in the southern islands.
Curbing and stamped concrete on the southern islands of the new SR 18 diverging diamond interchange.
---
We are on Day 4 of our 5-day closure of SR 18 at I-90. What have we been up to? SO glad you asked. A summary of our work so far:
- Asphalt removal as we build the new diverging diamond interchange (DDI)
- New pavement on the DDI's south end
- Added drainage, electrical wiring, curbing and a new sign bridge on the south end of the DDI
- Started on the southern islands of the DDI with curbing and stamped concrete pours
- Said hi to some deer that came to visit (see photo)
We're still on track to reopen this interchange by 5 a.m. Wednesday, June 4. Thank you for your continued patience!
Note: These photos are from Sunday, June 1. We do not yet have visuals of today's work.