Same spot. Six weeks apart.
This San Jose backyard was straight dirt when we started. Out front: red mulch, dead trees, and a lot of rocks.
What we did: → Drought-tolerant gravel up front → New driveway, new fence, a lot of concrete → Rebuilt the front porch with an acrylic-covered pergola → Artificial turf and a deck out back → Awnings, so he can sit outside even when it rains → Accent lights through the yard and around every deck edge → Extra outdoor outlets, so Christmas lights don't need a single extension cord
Old house, so there were surprises. There always are. The big one: the main water supply line had rusted out. Since the front yard was already torn up for landscaping, we swapped the whole line then. Way better than digging up a brand-new yard to fix it later. Still wrapped in six weeks.