05/01/2026
Momentum continues to build at the Riverbend Athletic Complex in Woodruff, SC.
Site retaining walls are officially underway, marking a major milestone and a significant turning point for the project. This work opens up multiple areas of the site for foundations and future vertical construction.
At the same time, mass grading is nearing the finish line, blasting is complete, and crews are continuing to advance storm and sewer, GAB, and site prep across the property. Asphalt is up next as the project shifts from heavy dirt work into more defined infrastructure.
This is the phase where the vision starts to become reality. The pace, coordination, and commitment from our City partners, field teams, and trade partners continues to stand out.