08/04/2026
Project Update in Starke, Florida – Progress is Moving!
Another milestone reached!
Our footers have been excavated, formed, reinforced, and passed inspection. These have to be some of the cleanest footers we’ve put in the ground—they came out fantastic.
Don’t mind the standing water—we’ve had a lot of rain lately, but the footing trenches are ready to go. Concrete is being poured today, and if everything stays on schedule, we’ll have the stem wall completed this week and will be going vertical with framing next week!
It’s always exciting to see a project transition from dirt work to the actual structure taking shape.
Stay tuned for more updates as this home starts coming out of the ground!
🏠 JBH Custom Homes & Remodeling
Building quality from the ground up.