Sealevel Construction Inc.

Sealevel Construction Inc. Sealevel Construction is a locally owned heavy civil contractor founded in Southeast, Louisiana in 1997.

06/03/2026

PROJECT SPOTLIGHT: Sealevel is wrapping up work on the Reach L Floodwall Project for the Terrebonne Levee & Conservation District (TLCD) in Cut Off, LA.

Our crews have completed the sheet pile floodwall, including four pipeline penetrations and final levee tie-ins, now providing critical flood protection for the area. The project included the installation of 110 plumb and battered H-piles along with more than 100 pairs of sheet piles, forming a key component of the region’s overall protection system.

We’re proud of the work our team continues to deliver in strengthening coastal protection infrastructure across South Louisiana!

06/03/2026

Since 1968, the South Lafourche Levee District has had one job: keep the water out.

For more than 55 years, we have built, maintained, and improved the flood protection system that stands between this community and the waterways that surround our community. That work does not stop.

The work is easy to take for granted. That is why we want to make sure South Lafourche never forgets what it means.

South Lafourche. Protected.

05/27/2026

PROJECT UPDATE: A monumental milestone achieved for the Bayou Lafourche Pump Station project as Sealevel successfully set four massive pumps — each measuring 68 feet long, 7 feet in diameter, and weighing 92,000 lbs., making them the tallest pumps ever built by the manufacturer.

What was planned as a three-day operation was completed in just one day thanks to the flawless ex*****on, precise coordination, and exceptional craftsmanship from the Sealevel team.

This high-risk lift required zero room for error:
▪️ 750-ton crane utilized
▪️ 72” piping cast directly into concrete walls with exact alignment
▪️ Precision installation of anchor bolts
▪️ Six pump locations prepared— four installed with two future installations
▪️ Elevated precision work performed across multiple Sealevel trade crews

From site prep and logistics to transport, lift support, and final placement, Sealevel self-performed the operation. The level of planning, communication, and precision made this massive lift look routine, an incredible accomplishment by the entire team!

Sealevel is proud to be a part of the Southeast Louisiana Urban Drainage Flood Control Project (SELA 26.1a) in New Orlea...
05/22/2026

Sealevel is proud to be a part of the Southeast Louisiana Urban Drainage Flood Control Project (SELA 26.1a) in New Orleans.

The first cofferdam is now underway using our GIKEN Silent Piler, selected for its ability to operate efficiently in dense urban environments near rail lines and sensitive utilities while greatly reducing noise and vibration impacts to the surrounding community.

Our team is making steady progress along Florida Avenue in New Orleans’ Desire neighborhood (Gentilly/Upper 9th Ward) as part of the Southeast Louisiana Urban Drainage Flood Control Project (SELA 26.1a).

Construction crews are currently installing sheet piles for a Temporary Retaining Structure (TRS), which helps safely hold back soil and groundwater during construction while utilities and foundations are installed. By using the GIKEN Hammer system, we’re able to complete this work with significantly reduced noise and vibration, helping minimize impacts to nearby residents while construction moves forward.

These critical drainage improvements are part of the parish’s master drainage plan and are designed to help reduce flood risk from heavy rainfall events up to a 10-year storm. Once complete, the upgrades will strengthen infrastructure, improve stormwater management, and support a more resilient future for the community.

Every step forward brings us closer to a safer, stronger New Orleans.

05/18/2026

Sealevel celebrated its 6th Annual Family Day this past weekend with great food, music, activities, and fun!

Congratulations to our co****le champions, and a big thank you to all of our employees and their families who came out and joined in the festivities.

05/13/2026

PROJECT UPDATE: Sealevel continues to make major strides on the HNC Lock Complex Project, achieving significant milestones and driving progress forward through the hard work and dedication of our teams on site.

Over the past year, substantial advancements have been made as we remain on track toward successful project completion.

Key Milestones Achieved:
✅ Completion of the operations area bulkhead installation
✅ Completion of control house piling
✅ Installation of both Gulf and Inland side cofferdams
✅ Completion of pile driving for all GSSG (Gulf Side Sector Gate) & ISSG (Inland Side Sector Gate) foundation piles
✅ Placed both tremie slabs for GSSG & ISSG foundations
✅ Completion of mechanical dredging
✅ Completion of nose pier construction
✅ Completion of the access bridge

Ongoing Work:
• Installation of lock chamber plumb and batter piles
• Timber fender system installation
• Reinforcement of steel installation and subsequent concrete placement for both Inland and Gulf Side Sector gates

Quantities Installed To Date:
• Steel Pipe Pile — 131,983 LF
• Precast Concrete Pile — 8,710 LF
• Sheet Pile — 164,463 SF
• CIP Concrete — 23,441 CY

This continued progress reflects the dedication, expertise, and teamwork of everyone involved, and we appreciate the hard work and commitment driving the ongoing success of this critical infrastructure project!

Sealevel is proud to announce that we have earned the ABC STEP Diamond Award from the ABC Greater Houston Chapter, the h...
05/01/2026

Sealevel is proud to announce that we have earned the ABC STEP Diamond Award from the ABC Greater Houston Chapter, the highest level of recognition for safety excellence.

This achievement reflects our company-wide commitment to maintaining a strong safety-first culture through leadership, accountability, and continuous training. Congratulations to our team, and thank you to everyone who makes safety a core value both on and off the job site!

04/28/2026

PROJECT UPDATE: Sealevel has successfully removed the first tainter gate—an incredible milestone on the Red River Lock and Dam No. 1 Tainter Gate Replacement project.

Installed in 1979, this 182,526 lb gate was safely extracted in one piece, overcoming significant constraints and expectations. With just 2 inches of clearance on each side, the team executed the lift without any damage to the surrounding concrete or structure.

This is another strong example of precise planning and ex*****on delivering a successful outcome. Great work, team!

Thank you to everyone who came out and joined us for Sealevel's 6th Annual Day on the Greens! Congratulations to our fiv...
04/13/2026

Thank you to everyone who came out and joined us for Sealevel's 6th Annual Day on the Greens!

Congratulations to our five winning teams, and a huge shoutout to our hole sponsors and winner/door prize sponsors for their generous support. We appreciate each of you and look forward to another fantastic tournament next year!

Address

1087 Highway 3185
Thibodaux, LA
70301

Alerts

Be the first to know and let us send you an email when Sealevel Construction Inc. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Sealevel Construction Inc.:

Share