12/22/2023
Diamondback Industrial Progress 12/22/2023
Office drywall 95% complete, Ground level being finished and prepped for paint.
Stairwell 2 and 3 framed and drywall hung.
Stairs 2 and 3 have been concrete filled.
Stairwell 1 being fabricated.
Two line rail installed at inventory/fab area.
Electrical service continued at warehouse space.
Grinding/sanding room complete.
Parts office framed and drywall hung
Waterjet room complete.
Concrete paving at line 32 endwall complete.
Concrete paving at line B sidewall complete.
Compressor canopy 90% complete.
Rear lean too primary and secondary steel complete.
NW bathroom bank in progress.
Waterjet office drywall being hung.
Central bathroom ready for drywall.
West lean-to primary and secondary steel complete, roof 95%.
Underground structures being set around front pond.
Fire protection water line being ran.
Concrete prep started for covered outdoor display.