Brevard Constructors, Inc.

Brevard Constructors, Inc. Commercial and Industrial General Contractor.

Diamondback Industrial Progress 12/22/2023Office drywall 95% complete, Ground level being finished and prepped for paint...
12/22/2023

Diamondback Industrial Progress 12/22/2023
Office drywall 95% complete, Ground level being finished and prepped for paint.
Stairwell 2 and 3 framed and drywall hung.
Stairs 2 and 3 have been concrete filled.
Stairwell 1 being fabricated.
Two line rail installed at inventory/fab area.
Electrical service continued at warehouse space.
Grinding/sanding room complete.
Parts office framed and drywall hung
Waterjet room complete.
Concrete paving at line 32 endwall complete.
Concrete paving at line B sidewall complete.
Compressor canopy 90% complete.
Rear lean too primary and secondary steel complete.
NW bathroom bank in progress.
Waterjet office drywall being hung.
Central bathroom ready for drywall.
West lean-to primary and secondary steel complete, roof 95%.
Underground structures being set around front pond.
Fire protection water line being ran.
Concrete prep started for covered outdoor display.

Diamondback Industrial Progress 11/03/23Roof drains being installed along Line B sidewall.Wall sheeting at line B sidewa...
11/06/2023

Diamondback Industrial Progress 11/03/23

Roof drains being installed along Line B sidewall.
Wall sheeting at line B sidewall complete.
Wall sheeting at line S sidewall complete.
Wall sheeting continued at partition line k.
Fixed glass frames being installed and sealed in line S sidewall.
Water lines being ran from building to parking lot island.
Roof installed on lean to 3.
Roll up doors being installed at line 32 endwall and line B sidewall.
Waterjet room being fabricated.
Back ponds being shaped up, ready to dig.
Wall sheeting continued at line 2 endwall.
Wall boards delivered, and being hung one side at mezzanine level.
Warehouse stairs 1 and 2 delivered and installed.
Water and sanitary sewer in office area near complete.
Multiple inspections passed.

Auxiliary Building
11/02/2023

Auxiliary Building

Fleet Facility
10/25/2023

Fleet Facility

CFR roof continued lines 17 thru 5, B thru K .Sanitary being surveyed and well points being installed.Back two ponds hav...
10/09/2023

CFR roof continued lines 17 thru 5, B thru K .
Sanitary being surveyed and well points being installed.
Back two ponds having stripping's removed.
Framing continued in warehouse space at central bathrooms, parts office, water jet office and north restrooms.
Plumbing rough-in continued at ground level and mezzanine level office area.
Electrical rough-in continued at ground level and mezzanine level office area.
Hvac continued at ground level and mezzanine level office area.
Fire protection continued at warehouse area.
Drywall being finished in upper areas of office space.
Drywall primed and ready for paint on upper office areas.
Center wall being sheeted, Lines 23 thru 14 complete.

Diamondback Industrial Progress 09/22/2023CFR roof continued lines 29 thru 17, B thru K complete.CFR roof continued, lin...
09/25/2023

Diamondback Industrial Progress 09/22/2023

CFR roof continued lines 29 thru 17, B thru K complete.
CFR roof continued, lines 10 thru 2, K thru S complete. North side complete.
Retaining wall finished and waterproofed.
Underground structures arriving.
Back two ponds have been surveyed.
Debris clearing and burning complete at back two ponds.
Framing continued in warehouse space at central bathrooms, parts office, water jet office and north restrooms.
Plumbing rough in continued at ground level and mezzanine level office area.
Electrical rough in continued at ground level and mezzanine level office area.
HVAC continued at ground level and mezzanine level office area.
Fire protection continued at warehouse area.
Drywall being finished in upper areas of office space.
Multiple inspections passed.

Former "Mims Citrus" property refurbishment.
09/20/2023

Former "Mims Citrus" property refurbishment.

Water Reclamation Facility completed.
09/12/2023

Water Reclamation Facility completed.

Diamondback Industrial Progress 09/08/2023CFR roof continued lines 31 thru 29, B thru K  complete.CFR roof panel bundles...
09/11/2023

Diamondback Industrial Progress 09/08/2023

CFR roof continued lines 31 thru 29, B thru K complete.
CFR roof panel bundles set on the remainder of the PEMB.
CFR roof continued, lines 10 thru 14, K thru S complete.
Retaining wall steel continued, Portions of wall poured.
Water proofing started and continued at retaining wall.
Underground structures arriving.
Framing continued in warehouse space at central bathrooms, parts office and water jet office.
Plumbing rough in continued at ground level office area.
Electrical rough in continued at ground level and mezzanine level office area.
HVAC continued at ground level office area.
Fire suppression continued at mezzanine level office area.
Drywall hung in upper areas of office space.
Multiple inspections passed.

Diamondback Industrial Progress 08/25/2023Excavations continued at retaining wall around wetland 2.Rebar tied, set and c...
08/28/2023

Diamondback Industrial Progress 08/25/2023

Excavations continued at retaining wall around wetland 2.
Rebar tied, set and concrete poured at retaining wall.
Fixed glass windows and store front frames set, and glass installed at office space.
Glass garage doors installed.
Framing continued in office space at ground and mezzanine level.
HVAC continued at mezzanine level, material arrival for ground level.
Electrical continued at office ground level.
Fire protection continued in office and warehouse spaces.
Overhead crane rails installed, overhead crane arrival and set in place.
Wall layout continued at central warehouse bathrooms, waterjet offices and tool storage.
Secondary steel finished warehouse space.
Roof started at warehouse space line 32 thru 31, B thru K.
Front sidewall sheeting continued line S, 5 thru 7.
Front pond being pumped down to continue dirt work.

Diamondback Industrial Progress 08/18/2023Secondary steel complete, K thru S, 2 thru 10.Secondary steel continued, B thr...
08/21/2023

Diamondback Industrial Progress 08/18/2023

Secondary steel complete, K thru S, 2 thru 10.
Secondary steel continued, B thru K, 2 thru 10.
Endwall sheeting complete at line 32, above and below lean to 3.
Sidewall sheeting started and continued at line B. 32 thru 29 complete.
Metal framing continued in office space at ground level, and mezzanine level.
Drywall being hung in hard to access areas.
HVAC continued in office at ground and mezzanine level.
Electrical continued in office space at ground level.
CMU openings being primed for fixed glass frames.
Fire protection started and continued in warehouse and office space.

Address

2023 N. Carpenter Road
Titusville, FL
32796

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 3pm

Telephone

+13212692929

Alerts

Be the first to know and let us send you an email when Brevard Constructors, Inc. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Brevard Constructors, Inc.:

Share