02/09/2023
Aerial View. NE 25th Ct, Fort Lauderdale, FL.
Completed Phases: Grade Beam Footers, Stemwall Masonry, Stemwall Cells and Tie Column Pour, Monolithic Thickened Edge Slab, Pool Deck Extension, 1st lift masonry, 1st lift Concrete infill @ edges of Hollow Core System, 1st Lift Tie Beam, 2nd floor Concrete Deck Areas and eyebrows, 2nd floor elevated Jaccuzi Area, 2nd Masonry, 2nd lift Concrete infill @ edges of Hollow Core System, 2nd Lift Tie Beam, 3rd floor concrete eyebrows, 3rd Lift Masonry, 3rd lift Concrete infill @ edges of Hollow Core System, 3rd Lift Tie Beam, Roof Concrete Deck Areas and eyebrows, and Red Iron Curtain Wall System.
Retaining walls around perimeter of the house: Spread footings, Masonry, 8x8 Concrete cap.