03/31/2026
As projects pushed through winter conditions and into more active construction phases, the first quarter of 2026 has brought steady, visible progress across our jobsites. From early-stage site work to buildings taking shape and nearing completion, our teams have kept momentum moving in the right direction.
• D'Orazio Ford - After a planned winter break, work at the D’Orazio Ford project picked back up quickly, with the pre-engineered metal building assembly nearing completion. The building is taking shape and allowing interior work to begin—marking a significant transition into the next phase of construction—as roofing wraps up and underground utilities resume ahead of under-slab equipment installation.
• Chase Bank Skokie Touhy - Since breaking ground in December, the Chase Bank project in Skokie has been progressing steadily through exterior construction, with the building envelope set to be completed this week. Interior work is ramping up as electrical rough-in wraps up and drywall installation begins.
• Advantage Honda of Fox Lake - Work at Advantage Honda of Fox Lake continues to progress, with painting finishing up and lighting fixtures being installed throughout the facility. Epoxy flooring is now underway, paving the way for the owner’s vendors to move in and install lifts, benches, and other equipment.
• Chase Bank East Peoria - The new ground-up Chase Bank in East Peoria is now complete, with signage installed all inspections finalized, marking the closeout of the project.
• Dogtopia - The Dogtopia build-out is progressing as plumbing, electrical, and HVAC rough-ins continue. Wall framing is now underway, and the installation of acoustical soundproofing drywall for the ceiling has also begun to minimize sound transfer throughout the space above.
• Chase Bank Oak Lawn - Construction has kicked off on a new ground-up Chase Bank in Oak Lawn, with demolition of the existing building already in progress. This initial phase sets the stage for site preparation and upcoming foundation work.
Progress like this doesn’t happen without strong coordination in the field. It’s been a productive first quarter across our jobsites, and we’re looking forward to keeping things moving as these projects continue to develop in the coming months.