SAUDI PROJECT | 25 CONTAINERS, 13 SHIPMENTS, ONE COORDINATED PLANT
A plant built in one country and installed in another is only as strong as the planning behind every delivery.
Once Bendet completed the design & planning phase, the focus shifted to turning approved engineering information into procured materials, fabricated equipment and installation-ready components.
For this industrial wet-spray paint plant in Saudi Arabia, Bendet kept procurement tightly aligned with design releases, fabrication priorities & the planned installation sequence, coordinating materials, manufactured components & specialist equipment from local & international suppliers.
Bendet tracked long-lead & specialist items against the project programme, so fabrication could start on available materials while outstanding components were still being sourced.
As materials arrived, Bendet moved straight into fabrication & preassembly. Components and assemblies were checked before dispatch for dimensions, fitment & interfaces, so potential installation concerns were picked up in the workshop rather than discovered on site.
The logistics alone show the scale of the task: 25 off 40ft High Cube containers dispatched across 13 sea-freight shipments, supported by two airfreight shipments from Italy & two from South Africa.
Then the programme was put to the test. Regional shipping disruptions extended some delivery windows by approximately 20 to 50 days, & the loading sequence could not guarantee the order in which shipments would reach site.
This is where Bendet's planning made the difference. Procurement, fabrication, packing & installation priorities were coordinated through one project programme. Every component was identified, grouped and packed according to the installation requirements, so the site team knew where each item belonged & when it would be needed.
When materials arrived out of sequence, Bendet did not stand still. The team prepared the remaining components and progressed the sections for which equipment was available, keeping productive work moving while outstanding deliveries were in transit.
Bendet's experienced core installation team carried the project knowledge through to site & guided local labour during ex*****on. Detailed planning, clear communication & close cooperation with suppliers & other contractors allowed Bendet to adapt to changing delivery and site conditions while maintaining the project's technical requirements.
Fabrication capability matters. Delivering it across borders, through disruption & out of sequence, is the real test.
Contact Bendet Engineering Services to discuss how our expertise can be planned around your installation programme from the outset on
✉️ [email protected]
Follow the Saudi Project Series as the equipment moves from packaged components to installation on site.