Project : Water Road Alterations & Additions
Week 3 :
It’s been a while !!!!! had to wait 4 weeks for clear sky and minimal wind in order to open up existing roof and to close roof which required 3 days of good weather to ensure no damage to existing house
In single week we now managed to complete roof and eaves, fit window, complete all plaster internally and externally, plus fit skimmed ceiling and decorative cornices
BUCO Port Elizabeth North End, Glendore Sand and Stone, City Paint & Tool, C and T Truss Solutions, Zurchers Electrical, Lloyd's Plumbers