Complex projects call for smart solutions.
Chadoak Plumbing & Drainage recently completed this impressive 7-metre-deep manhole in Victoria while working on a live sewer.
To safely construct the manhole, the team first diverted the live sewer around the excavation, allowing the base and first lift to be poured. The sewer was then reinstated through the new manhole before the structure was raised another 3.5 metres to its final height, with the final lifts completed once surrounding works were finished.
This is exactly the kind of project where Manhole Form Hire's modular formwork comes into its own. Our systems are designed to help contractors tackle challenging manhole construction with confidence, adapting to staged construction and complex site conditions.
We're proud to have supported Chadoak on another outstanding project and love seeing our forms helping crews deliver quality results across Australia.