In regards to a post about a disgruntled client.
Unfortunately when we are provided with incorrect information it can put a project back.
When it comes to asbestos removal it is of utmost importance to supply the correct information to the government or it will result in major set backs.
The time spent arranging materials mobilisation of employees, equipment, and having to put other jobs back.
When you do asbestos work the address where the tests are done must be the location of the asbestos removal.
This letter addresses your cancellation of the asbestos removal project, your request for reimbursement of the $2,000 mobilization fee, and the repeated attempts to change the scope of work.
The project experienced delays after the property address provided for the asbestos project notification was found to be incorrect. Accurate work-site information is necessary for the notification process, and correcting the information affected the project schedule.
In addition, the scope of work has been repeatedly revised or challenged during the project discussions. Each change required additional review, clarification, planning, and coordination. These ongoing scope changes made it difficult to finalize the work requirements, pricing, scheduling, and regulatory preparations necessary to proceed.
Our position is that the incorrect address information and repeated scope changes contributed to the resulting delays and must be considered when determining responsibility for the cancellation and any associated costs.
Prior to cancellation, our company had already devoted time and resources to project preparation, administration, scheduling, scope review, and mobilization-related activities. These efforts represent work undertaken in preparation for the project and must be considered in any fair assessment of the requested reimbursement.
We do not agree that cancellation alone automatically entitles you to a full refund of the mobilization fee. The appropriate amount, if any, must be assessed in light of the work performed, documented expenses, scope changes requested, information supplied by both parties, and the terms of our agreement.
We are prepared to provide a reasonable breakdown of the work completed and costs incurred. We reserve our position regarding any documented losses arising from the incorrect information, repeated scope changes, and subsequent cancellation.
Please direct any further correspondence regarding the cancellation, reimbursement request, or scope of work in writing so that the matter can be addressed using the project records. Any proposed change to the scope must be clearly documented and agreed upon before additional work, costs, or scheduling commitments are undertaken.
Sincerely,
Ben Waitson Demolition & Hazmat