What our R&D process looks like
Blauberg Motoren has its own R&D team that oversees development from the initial technical inquiry through to the launch of the product into mass production. Our approach to development depends on the type of task and this is what determines the timeline and complexity of implementation.
We distinguish between two types of development:
- Customization of the existing product line adapting existing fans to specific customer requirements: changing the wire length, installing a special connector, adjusting power, changing the impeller press-fit depth, etc. For EC fans, changes to aerodynamic characteristics are achieved by adjusting software parameters, whereas for AC fans, this requires modifying the stator winding;
- Development of new solutions creating highly customized or fundamentally new designs that are not currently in the company’s portfolio.
Regardless of the type, the process follows the same stages:
1. Assessment of the request and project approval with the client;
2. Development of design documentation by the R&D team;
3. Manufacturing or ordering production tooling (if necessary);
4. Assembly of a prototype and transfer to the laboratory;
5. Conducting aerodynamic and climatic tests;
6. Client approval of the results and launch into mass production.
Delivery times for standard customizations range from 4 to 6 weeks. More complex projects requiring the manufacture of additional tooling or the development of new design solutions have customized delivery schedules. We are open to any inquiry and it is our in-house R&D team that allows us to respond flexibly to the needs of each client.