03/11/2026
30MW. Level 2 and 3 deadlines already under pressure. And no commissioning team in place.
That was the starting point.
Fourteen days later there were six engineers on site. Low-voltage, high-voltage, mechanical. One of them stepped into the site lead role and ran the daily coordination between client, end-client and the other contractors.
Five months later, every system was signed off and the existing delays had been pulled back.
The collaboration is still running on new sites across Europe.
Swipe for how it was put together.
Link to full case in comments 👇