07/09/2026
Our South and Central team continues to make great progress on the Luton Station Access for All project on behalf of Network Rail.
All three lift shafts are now installed and bridge steelwork is advancing across the island platforms. The focus remains on completing the new bridge structure by the end of September, which will mark a significant milestone in the project.
Once the steelwork is in place, works will progress to fitting out the three lifts, completing the bridge interiors and renewing platform lighting, ahead of bringing the new accessible route into service.