Renovate - sw Ltd

Renovate - sw Ltd local building company what focuses on, full renovations, extensions, conversions & general building

Another week done New house roof and extension roof on front and gable all rendered except the front door wall and plint...
27/03/2026

Another week done
New house roof and extension roof on
front and gable all rendered except the front door wall and plinths to be top coated
Front door going in next week
Both bi-folds in the extension going in next week
Gas main all dug ready for next week
All rooms skimmed and painted
All facials and soffits and guttering done
Second fix on bathrooms being done
Kitchen being fitted
And ground works next week
And rendering the extension
Steps being build next week
Couple weeks then it's a wrap

Progress update... here's just a few of progress pictures would be a lot further on but customer decided he wants a full...
15/02/2026

Progress update... here's just a few of progress pictures would be a lot further on but customer decided he wants a full new roof to match the extension but we is battling against the weather cus we can't get the vally cut in due just need a break so both roofs can go on and water tight again

WATER STILL COMING IN AFTER NEARLY FINISHED OUT SIDE ......we thought it was the hight water table and pushing up thru t...
15/02/2026

WATER STILL COMING IN AFTER NEARLY FINISHED OUT SIDE ......we thought it was the hight water table and pushing up thru the old cellar floor so I wasnt happy and decided to investigate to relise it was coming in thru the perk joints so took down retaining wall ripped up all the slabs and dug it all out again to realise we just didn't tank down far enough...so we dug down deeper tanked it all then rendered it then decided to put capping beam around all that area. took all the back fill out from behind the reatianing wall as the rain was missing the weep holes and running right along the footing and going to the lowest corner witch happend to be were the water was coming in...now started putting it all back together and so far it's been dry inside.. we done all this of my own back free of charge cus we should
Of spotted it when we done it the first time but we didn't have any rain at the time so glad we didn't start the inside just yet # #🤦‍♂️

This flat has come available Fully refurbished 3 bedroom flat with office and living room and main bathroom and bedroom ...
15/02/2026

This flat has come available Fully refurbished 3 bedroom flat with office and living room and main bathroom and bedroom with en-suite parking and maybe available garage in nice quite spot in Lympstone
Give us a shout if interested and let you no more details

24/12/2025

From renovate and Arch plastering & dry lining contractors ltd we wish you all a merry Xmas and a happy new year

All the load bearing walls up on the heavitree job also  retaining wall out the ground and all the drainage in and block...
20/11/2025

All the load bearing walls up on the heavitree job also retaining wall out the ground and all the drainage in and block work up to dpc level and steels in for the bi-fold doors just waiting on the columns to take the ridge beam 

11/11/2025

Nearly of this floor final touch's and carpets soon big difference a lot of work has gone into this befor and after pic coming soon now we're getting it water tight down stairs

11/11/2025

Full steam ahead on our Exeter job as well as Lympstone busy times

11/11/2025

Full steam ahead on the heavitree job as well as Lympstone busy times

2 more of theses to knock out and windows and doors are ready to go in to get it all water tight down on the ground floo...
27/10/2025

2 more of theses to knock out and windows and doors are ready to go in to get it all water tight down on the ground floor on the Lympstone job

Progress pic Here the job in Lympstone full rip out Ground floor has had a lot done.all the door lintels raised walls kn...
17/10/2025

Progress pic
Here the job in Lympstone full rip out
Ground floor has had a lot done.all the door lintels raised walls knocked down steels put in and extra windows put in for more light and tanking...First floor full rip out all external walls studded if and insulated.boared and skimming new suspended ceilings.put in extra family bathroom..all new electrics and plumbing...and in middle of being decorated..out side dig down tank all the walls put in new retaining wall and steps...keep eye out for more progress pics soon

Address

Wilford Road
Exeter
EX25LD

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm
Saturday 9am - 3pm

Telephone

+447593299829

Alerts

Be the first to know and let us send you an email when Renovate - sw Ltd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share