Connect Construction

Connect Construction UK based contractor specialising in construction of guide walls for the piling industry.

Last week we completed delivery of a King Post Retaining Wall and Raft Slab project at  for  in close collaboration with...
06/05/2026

Last week we completed delivery of a King Post Retaining Wall and Raft Slab project at for in close collaboration with

This project is a great example of the value of strong collaboration, coordinated delivery, and streamlined communication throughout every phase of construction. From initial design development through to final handover, EQUANS benefited from a single point of contact across the entire project - ensuring clear communication and smooth approval of every stage of the works.

Working alongside Helical Pile Solutions Ltd, we delivered the following:
- WAC testing
- Vacuum excavation around existing services to identify and mark underground services prior to piling
- Supply and installation of precast units between piles
- Installation of uPVC drainage pipework
- Connections into the existing 450mm manholes
- Construction of reinforced in-situ concrete raft slab
- Supply and installation of M100 ACO drainage channels cast into the slab
- Installation of concrete paving slabs

A huge thank you to everyone involved in the successful delivery of this project. Collaborative working relationships such as these continue to demonstrate the importance of teamwork, technical expertise, and reliable project coordination in delivering high-quality results safely and efficiently.

Last week, we successfully completed a major reinforced concrete package delivered as part of a significant rail infrast...
14/04/2026

Last week, we successfully completed a major reinforced concrete package delivered as part of a significant rail infrastructure upgrade in the North of England, having commenced works in October 2025.

Our scope of works included:
- 28 pile caps
- 3 lift pits
- 9 finger canopies
- 3 concrete slabs

All delivered within a busy high-street and highly disruptive live environment.

To meet programme demands, we mobilised four gangs, supported by 5 supervisors and 2 setting-out engineers, undertaking a full package of excavation, pile cropping, blinding, formwork, reinforcement, gas membrane installation, waterproofing, concrete pours, drainage, ducting, backfilling, and finishing works.

Completing a project of this complexity weeks ahead of programme and with zero non-conformances is an achievement we are extremely proud of.

A huge thank you to our dedicated site team for their hard work and professionalism throughout, and to our valued supply chain partners for their continued support in helping us achieve this result.
We also extend our thanks to our client for trusting us to deliver this critical infrastructure package.

Another successful project delivered safely, efficiently, and to the highest standard.

ReinforcedConcrete SafetyFirst

Last November, we completed the construction of a capping beam (1850mm x 850mm) for   as part of the Torside Reservoir p...
19/01/2026

Last November, we completed the construction of a capping beam (1850mm x 850mm) for as part of the Torside Reservoir project.

Being self-sufficient on site, we provided all the necessary resources, plant, equipment, and materials to deliver:

- Formwork design
- Groundwater drainage from behind the capping beam, crossing underneath to divert water to the reservoir
- Pile cropping
- Installation of couplers to extend pile rebars
- CHS tubes to enable crossing anchors
- Construction of the capping beam (1.850m x 0.85m x 65m)
- Backfilling behind the capping beam

A specific sequencing was meticulously planned to mitigate any
bank movement during construction. GEO-Instruments team closely monitored progress through an observational monitoring method.

This was a challenging project, but our workforce made it look easy. Completing such a technical job a week ahead of schedule and with zero non-conformance is an achievement we are proud of.

I would like to take this opportunity to thank our team for their dedication, attitude, and professionalism, as well as our suppliers (Holcim UK, ROE BROS. & CO LTD., Deltashor, Cleveland Steel & Tubes Ltd, RUTTLE PLANT, BULLEN PLANT HIRE LIMITED, and others) for their proactive support, and of course, we thank our client for trusting us to deliver.

We are very proud to add KELLER to our list of prestigious clients and look forward to more collaboration in future.

We’re pleased to share the completion of another guide walls visit for . Due to ongoing activities on site, we were requ...
29/09/2025

We’re pleased to share the completion of another guide walls visit for .

Due to ongoing activities on site, we were requested to pour 25 meters of guide walls Friday and demobilise by Saturday to minimise interfaces with site operations.

We have delivered this as per our client’s request, at no extra charge, ensuring the project stays on track without disruption.

If you’re looking for a reliable, flexible, and professional contractor for your , , , , or , consider Connect Construction. Visit our website at www.connect-construction.co.uk to see more of our completed projects and references.

Thanks to our team and all involved for their hard work and dedication. Looking forward to more collaborations and successful milestones ahead.

We’re pleased to share the completion of the guide wall construction in Paddington, London, in partnership with  for our...
28/08/2025

We’re pleased to share the completion of the guide wall construction in Paddington, London, in partnership with for our repeat client,

Thanks for your continued trust. Looking forward to working together on more projects.

Last week, we wrapped up the secant piles guide walls construction in Kensington, London, for our repeat client,  & Allu...
29/07/2025

Last week, we wrapped up the secant piles guide walls construction in Kensington, London, for our repeat client, & Alluvium Elle. Thanks for your continuous trust. Looking forward to future projects together!

Today, we successfully completed the construction of a 600mm x 800mm capping beam over a sheet piled wall for  in Southp...
24/06/2025

Today, we successfully completed the construction of a 600mm x 800mm capping beam over a sheet piled wall for in Southport.

Instead of traditional flame cutting (oxy-fuel cutting), we used a magnetic drill to create space for the crossing rebars within the sheet piles. This approach proved to be safer, cleaner, and far more efficient for this job.

A big thank you to for entrusting us, once again, to deliver your project and a big thank you to David, Adrian, Stelian, Iulian, and Roberto for your dedication and hard work.

🚧 Job Completion at Central Park Leisure Center 🚧We’re proud to share photos of the project completed this week at Centr...
03/06/2025

🚧 Job Completion at Central Park Leisure Center 🚧

We’re proud to share photos of the project completed this week at Central Park Leisure Center. Our team kicked off the works by creating a temporary car park to divert traffic from the active site, ensuring the center remained accessible to the public throughout.

The project involved coordinated piling bay excavations—done in an agreed sequence to facilitate helical piles installation. This was followed by backfilling and compaction, paving the way for the frames installation.

Outside the piling area, we carried out trenching, ducting installation, and extensive making-good, tarmacking, and reinstatement works—all sequenced meticulously to keep ongoing coactivity smooth and efficient until our final handover.

After three months of collaborative effort, we’re delighted to showcase these photos. If you’re seeking a transformation similar to this, rest assured that with and , we work seamlessly, safely, and efficiently from design through to completion—delivering the whole project with a single point of contact.

The surroundings of the Preston project are truly stunning, and we couldn’t limit ourselves to just a few photos — so he...
27/05/2025

The surroundings of the Preston project are truly stunning, and we couldn’t limit ourselves to just a few photos — so here are a dozen to capture the beauty of the site’s location.

The last one is from Vista project, formerly ITV’s headquarters, another landmark project.

Thank you to and for your continued trust. We are proud to expand our portfolio of iconic projects.

We’re very proud to welcome  to our list of clients! We successfully completed the construction of pile caps for them in...
29/04/2025

We’re very proud to welcome to our list of clients! We successfully completed the construction of pile caps for them in Redhill, which included the reinstatement of the footpath adjacent to the pile caps, and being completely self-sufficient on site.
A big thank you to Andy Howard for placing your trust in us for this project. We look forward to more collaborations in the near future!

Address

Avondale House, 262 Uxbridge Road
London
HA54HS

Alerts

Be the first to know and let us send you an email when Connect Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Connect Construction:

Featured

Share