14/08/2026
👷♂️ MEET SOME OF THE TEAM BEHIND ELITE BUILD NW 🏡
Another productive week on site and this one gives you a little look at some of the people behind the work, as well as the progress being made. 💪
This week we’ve completed:
🔩 Structural steels fully installed
🏗️ Acrows removed
⚡ First-fix electrics complete
🚿 First-fix plumbing complete
That means we’re now all set for insulation, dry lining and plastering to commence next week — when the transformation really starts to take shape. 👌
A successful project isn’t just about the finished result. It’s about having the right team, the right trades and keeping every stage of the build moving in the right order.
Proud of the team and another strong week of progress. 🙌