Last Wednesday night we teamed up with one of ur great partners for the placement of the last 7 girders spanning I-95 over Broadway in Bangor. Our Terex AC200-1 was tasked for the job with Dylan in the seat.
The beams were trucked to Bangor from South Portland and staged in a closure on the northbound passing lane. At 8pm Broadway was shut down and crew took the street. The beams weighing in at a modest 24,000lbs were placed along with diaphragms and cross bracing.
The last diaphragm was set in place and equipment cleared from Broadway long before it had to be opened back up to traffic.
While we're onto the next job, this one was bittersweet. It was the last one for our AC200-1. It's going to a great family owned company from Rhode Island to help build their company. For us, we're making room for something bigger to adapt to our growing needs.
The AC200-1 has been a workhorse in our fleet for years and has done many jobs big and small. Shout out to Dylan for giving her a proper send off on her last job.