Demolition works at the former Qenos Plastics and Elastomers sites are well underway, and you can already notice changes to the skyline and appearance as many of the major structures have been removed.

Demolition at the former Qenos Resins and Olefins sites will also commence soon. Ausdecom will be the principal contractor executing all demolition works at the Qenos Altona sites.

For any questions or information as demolition progresses Ausdecom can be contacted at [email protected]

Separately, the level crossing removal project (not associated with Qenos) is progressing on Maidstone Street. Please note part of the former Qenos Plastics site is being used as a laydown area and site compound for the project. This may impact local traffic as construction continues - visit https://bigbuild.vic.gov.au/projects/level-crossing-removal-project for details.

Send a message to learn more

22/05/2025

Demolition works at the former Qenos Elastomers & Plastics manufacturing sites are preparing to commence. The works are expected to take approximately 12 months, with activity occurring Monday to Saturday.
Throughout the demolition process, the sites will continue to be carefully managed to minimise any impact on the community.

We appreciate your understanding and support as this important phase of site transformation gets underway.

For any concerns, please contact our environmental action line
on 1800 061 050.

Send a message to learn more

25/02/2025

The cleaning of the effluent treatment area is progressing without significant odour. We are now entering the final phases of the cleaning and continue to have the potential for odour generation in the short term. An odour management plan remains in place for this work.

As previously communicated all cleaning activities are expected to be completed by the end of March.

We remain committed to minimizing any disruption to our local community and appreciate your understanding and support during this time.

For regular updates on any potential impacts, please visit the Qenos Altona page.

If you have any general inquiries, please contact Alan Findlay, Environmental Health Coordinator, at [email protected] or (03) 9258 7333. For immediate concerns, our Environmental Action Line is available 24/7 at 1800 061 050.

Send a message to learn more

28/01/2025

We are nearing the completion of the final cleaning phase of the Olefins Makesafe Project. This will include cleaning the effluent treatment area, which may lead to an increased potential for odour generation over the next 2–3 weeks. An odour management plan is in place for this work. Other equipment cleaning activities are expected to be completed by the end of March.

We remain committed to minimizing any disruption to our local community and appreciate your understanding and support during this time.

For regular updates on any potential impacts, please visit the Qenos Altona page.

If you have any general inquiries, please contact Alan Findlay, Environmental Health Coordinator, at [email protected] or (03) 9258 7333. For immediate concerns, our Environmental Action Line is available 24/7 at 1800 061 050.

Send a message to learn more

19/12/2024

We are pleased to inform you that the flaring phase of the Altona Olefins Plant Makesafe Project has now been successfully completed, and the Olefins Flare has been safely and permanently shut down. This milestone was achieved alongside the removal of most materials from the site.

The next phase of the Makesafe Project, which will continue until the first quarter of 2025, will involve the cleaning of several vessels and the effluent treatment area. While flaring has concluded, there may still be some odours related to the cleaning activities. As with previous phases, we are committed to minimizing any disruption and greatly appreciate your understanding during this time.

For updates on any potential impacts to the community, please visit the Qenos Altona page.

If you have any general inquiries, please contact Alan Findlay, Environmental Health Coordinator, at [email protected] or (03) 9258 7333. For immediate concerns, the Environmental Action Line is available 24/7 at 1800 061 050, where all reports are logged and promptly addressed

21/10/2024

Flaring activity update:
As previously communicated, there may be occasions of higher flaring for specific tasks as part of the Plant Makesafe Project. We want to inform you that there will be flaring activity occurring overnight on Tuesday, October 22nd, starting around 7pm and planned to conclude between 9am and 10am on Wednesday, October 23rd. The timing has been arranged to ensure that the peak flaring occurs during the day.

This flaring is necessary to ensure that all material is safely removed from our feedstock supplier's pipeline and is part of essential safety and maintenance operations. You may notice visible flames and hear noise during this time. While we aim to minimize any disruption, we appreciate your understanding as we carry out this activity.

Regular updates on potential community impacts, such as noise or odour, will be posted on the Qenos Altona page.
For general inquiries, contact Environmental Health Coordinator Alan Findlay at [email protected] or (03) 9258 7333. The Environmental Action Line (1800 061 050) is a 24-hour free-call hotline for reporting concerns about the Altona Chemical Complex. All reports are logged and investigated immediately.

Send a message to learn more

10/10/2024

Qenos Altona Shutdown Update – Completion and Ongoing Flaring

We are pleased to announce that the final shutdown of the Qenos Altona plant operations, which began on 30th September 2024, has been successfully completed.
As part of ongoing makesafe activities, occasional flaring will continue. This is a normal part of the process and will occur intermittently until February 2025 when the final flaring will occur. We will continue to actively manage the flare to minimize its impact, particularly during night-time hours.
Updates on potential community impacts, such as noise or odour, will continue to be posted here on the Qenos Altona page.
For general inquiries, you can still contact Environmental Health Coordinator Alan Findlay at [email protected] or (03) 9258 7333. The Environmental Action Line (1800 061 050) remains available 24/7 for reporting any concerns about the Altona Chemical Complex. All reports are logged and investigated promptly.
Thank you for your understanding and support.

Send a message to learn more

26/09/2024

Qenos Altona Final Shutdown Update

Qenos will begin its final shutdown on 30th September 2024, in two phases: Plant Operations shutdown and Plant Makesafe.
During the Plant Operations shutdown, there will be intermittent flaring as the Qenos Olefins plant winds down over 7 to 10 days. Qenos will actively manage the flare to minimize its impact on our neighbours, with an emphasis on reducing flaring as far as practical at night.
The Plant Makesafe phase will involve round-the-clock work, with a focus on noise minimisation during night hours. Low-level flaring will continue until February 2025, with occasional higher flaring for specific tasks. Night-time flaring will be managed to minimize disruption.
Regular updates on potential community impacts, such as noise or odour, will be posted on the Qenos Altona page.

For general inquiries, contact Environmental Health Coordinator Alan Findlay at [email protected] or (03) 9258 7333.
The Environmental Action Line (1800 061 050) is a 24-hour free-call hotline for reporting concerns about the Altona Chemical Complex. All reports are logged and investigated immediately.

Send a message to learn more

Qenos would like to invite the community to a meeting to discuss the permanent shutdown and make safe plans for the Qeno...
28/08/2024

Qenos would like to invite the community to a meeting to discuss the permanent shutdown and make safe plans for the Qenos Altona sites.

Date: Thursday,12th September 2024
Time: 5:30 pm for light snacks with meeting to start at 6:00 pm

Location: Qenos Olefins Training Centre cnr of Kororoit Ck Rd & Maidstone St, Altona (refer attached map) or you may attend by web conference.

Please register your attendance by Monday 9th September by contacting Rob Berton (Qenos Safety, Health & Environment Manager) via email [email protected] or phone (03) 9258 7333.
Please advise if you are attending via web conference so a link can be issued.

Refer previous Qenos Altona Facebook post for further background:
https://www.facebook.com/QenosAltona/posts/488091037286260?rdid=ROkXXa9cAVxVfnpK

Agenda

6:00 - 6:10 Welcome, introductions and
apologies

6:10 - 6:20 Agenda review
Community, regulator & visitor
discussion points

Raise any general business items

6:20 - 6:45 Qenos plant closure and make safe
update on company administration
process, key priorities,
stakeholder engagement and
timelines
Presented by: Qenos Deed
Administrators (McGrathNicol) &
Qenos representatives

6:45 - 7:00 General business

07/08/2024

During the course of April 2024, the Qenos Group was sold to LAOP BidCo Pty Ltd. On 17 April 2024, Jason Preston, Jason Ireland, Matthew Caddy and Damien Pasfield (of McGrathNicol) were appointed Voluntary Administrators of the Qenos Group.

On 23 May 2024, creditors of the Qenos Group resolved that the Qenos Group entities execute Deeds of Company Arrangement (DOCAs). The DOCAs were executed on 13 June 2024 with the Voluntary Administrators being appointed as Deed Administrators. The DOCAs provide funding to (i) facilitate the permanent shutdown and make safe of the Qenos Group sites at Altona, Vic and Botany, NSW, (ii) pay Qenos employee entitlements in full, and (iii) provide a return to ordinary unsecured creditors.

Following discussions with key stakeholders it has now been confirmed that the operations at Qenos' Altona Plants will take feed out by 30th September 2024 for the final time. Shutdown and make safe planning for these plants are well underway. Make safe activities will continue for several months, ultimately preparing the Plants to be demolished. During the make safe process it is possible that the community will observe changes in the noises and odours associated with our previous operations. Throughout the entirety of the make safe and remediation process the safety of our employees, the community and the environment remains our first priority.

We will update the community closer to the point of feed being taken out of the Olefins plant, which will result in periods of flaring.

For general enquires please contact our Environmental Health Coordinator Alan Findlay (email: [email protected] or phone:(03) 9258 7333).

The Environmental Action Line (1800 061 050) is a 24-hour free-call hotline that residents can call to report a potential problem related to the Altona Chemical Complex operation. Every call is recorded, and all calls are investigated immediately.