Dragline Shutdown Complete ✅
Another strong result from the Richglen team with the successful completion of works on a Bucyrus-Erie 2570 Dragline.
Over 28 days, the crew delivered more than 33,000 work hours RI-free, completing a major scope that included tub wear plate replacement, structural repairs, hoist, drag and swing gearing overhauls, along with a range of electrical upgrades ⚙️⚡
A fantastic effort by everyone involved, delivering the shutdown safely and efficiently while maintaining a strong focus on quality throughout the project 👷♂️
Another example of what can be achieved through careful planning, teamwork and commitment on site.