05/08/2026
π§ **Progress Update from Waterlooville!** π§
Work is moving forward at the former Barclays Bank in Waterlooville, where our team is installing a brand-new internal drainage system.
πΉ Floors have been precision saw-cut and broken out.
πΉ New foul drainage lines have been installed and are now ready to be backfilled with reinforced concrete, restoring the floor to its original level.
πΉ The existing manhole has been successfully bridged using spun steel pipe and Flexseal collars for a robust, long-lasting solution.
πΉ New trenches have also been excavated through the rear car park, allowing connections into the existing manhole network.
Another project progressing smoothly thanks to the hard work and expertise of the Slark Construction team. We look forward to sharing more updates as the transformation continues!