Interior lath inspection ✅️. Mike will start scratch tomorrow. Our customer is going to need to figure out his tile pret...
08/28/2026

Interior lath inspection ✅️. Mike will start scratch tomorrow. Our customer is going to need to figure out his tile pretty quickly.

Another good day. Patrick is getting the Hardie Plank siding and trim up. Mike actually got the paper and lath up in the...
08/27/2026

Another good day. Patrick is getting the Hardie Plank siding and trim up. Mike actually got the paper and lath up in the shower today but did I remember to take a picture this afternoon? Nope. Interior lath inspection tomorrow. I'll get pictures then.

Full house on this one today. Demetrio delivering water proofing paper, lath, and spec mix for Mike. Polo getting the st...
08/25/2026

Full house on this one today. Demetrio delivering water proofing paper, lath, and spec mix for Mike. Polo getting the stucco brown coat done. Patrick starting on the smooth Hardie Plank siding. Gustavo and Maria getting the new drywall primed.

I delivered 5 gallons of primer this morning and checked out the texture finished yesterday by Adam. Adam does a great j...
08/23/2026

I delivered 5 gallons of primer this morning and checked out the texture finished yesterday by Adam. Adam does a great job but he's my messiest guy and it's not even close. Gustavo and Maria will get everything primed tomorrow.

Bathroom changes coming!
08/20/2026

Bathroom changes coming!

Adam and Brandon handling the drywall and Polo getting the scratch coat going on stucco. I delivered the door today so P...
08/20/2026

Adam and Brandon handling the drywall and Polo getting the scratch coat going on stucco. I delivered the door today so Patrick can install that in the morning and Polo cna finish that last wall. Things are moving!

Made it back to get pictures and remove the lockbox from this bathroom remodel. While it is a relatively small bathroom,...
08/17/2026

Made it back to get pictures and remove the lockbox from this bathroom remodel. While it is a relatively small bathroom, we were able to remove a water heater closet and install a tankless unit outside which allowed us to relocate the toilet to the other wall and install a double vanity plus a decent size shower. That shampoo box is 40 X 18. Check out the huge recessed medicine cabinet.

08/17/2026

Victor, Emilio, and crew started this one Saturday. The hardscape is coming but we need to wait for the pool builder to finish the equipment pad and a retaining wall before we can pour up against them. In the meantime, we saw cut and trenched to pull electrical from the main panel to the back corner of the yard for a future pergola and trenched from the backyard to the front gutter for area drains.

Insulation inspection was last Thursday. Drywall nailing and exterior lath inspection this Tuesday. Rigo killed it Frida...
08/17/2026

Insulation inspection was last Thursday. Drywall nailing and exterior lath inspection this Tuesday. Rigo killed it Friday and Saturday.

Dan got the shower glass installed Saturday. Demetrio will be back tomorrow to button up.
08/11/2026

Dan got the shower glass installed Saturday. Demetrio will be back tomorrow to button up.

Address

22343 La Palma Avenue, Ste 109
Yorba Linda, CA
92887

Opening Hours

Monday 8am - 2pm
Tuesday 8am - 2pm
Wednesday 8am - 2pm
Thursday 8am - 2pm
Friday 8am - 2pm

Telephone

+17146959003

Alerts

Be the first to know and let us send you an email when Hingewerks posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Hingewerks:

Shortcuts

Share